DATE: August 14, 2024
TO: PPACG Board of Directors
FROM: Carol McBroom, Finance Director
SUBJECT: Building Project Update
ACTION REQUESTED: Information Only
SUMMARY
Trane began to install the Building Automation System in mid-June. The estimated project cost is $1,150,000. The scope of work includes automating the air handling system, updating valves and VAV boxes and replacing all piping. Overall, this project will increase efficiency, lower operating and maintenance costs and improve indoor air quality and occupant comfort.
UPDATE
After weeks of demolition in the lower level, Trane has started replacing plumbing, sheet metal, insulation, and control wiring. In the coming weeks, they will finish by replacing ceiling tiles, repairing drywall, and cleaning up. They will also transition to the upper level, which is less complex and estimated to take about 30 days. System testing and balancing will occur after construction is complete.
The project is estimated to be completed by September 13th, but the lower level, including the main conference room, will be back to business as usual by September 3rd.