Board of Directors – Nov. 13, 2024: CDOT Monthly Update
Slide 1
CDOT Projects within the Pikes Peak Area Council of Governments
Active Construction Projects within PPACG
- MAMSIP I-25 Reconstruction
- Powers/Airport Interchange
- I-25: Fillmore to GoG Reconstruction
- ADA Ramp Reconstruction various locations in Fountain, Colorado Springs, Monument & Palmer Lake
- Baptist Road/Terrazzo Roundabout
- US85/Carson Blvd T Intersection Improvements (continuous green NB)
- I-25 Resurfacing Midway MP 119-124
New 2024 Construction Projects within PPACG
- Emergency repairs to CBC southeast of Powers (CO21A)/Grinnell Blvd intersection
Planned Future 2025 Construction within PPACG:
- CO115 Resurfacing Nelson Blvd to Brookside –successful bid opening on Oct. 31st
- CO67D North of Woodland Park Improvements – re-AD in Nov.
Slide 2
Other CDOT Projects within the Central Front Range Area
Active Construction Projects within CFR
- CO115 Reconstruction MP 27-39 (El Paso)
- CO9/US285 Reconstruction – Intersection and Bridge (Park)
- CO9 Alma NB and US285 Grant WB Chain Up Stations (Park)
- US24G Resurfacing east of Falcon to east of Peyton (El Paso)
- US50 Resurfacing from Salida to Coaldale (Fremont)
New 2024 Construction Projects within PPACG
- Canon City Oil Creek Ditch Culvert Lining (Fremont)
Planned Future 2025 Construction within CFR:
- US24A Resurfacing Florissant through Divide (Teller) – AD in Nov.
- US285 Resurfacing through Bailey MP 220-228 (Park) – project is under AD
Slide 3
CDOT Projects within the Pikes Peak Area Council of Governments
Active Construction Projects within PPACG
- MAMSIP I-25 Reconstruction
- I-25: Fillmore to GoG Reconstruction
- ADA Ramp Reconstruction various locations in Fountain, Colorado Springs, Monument & Palmer Lake
- US24 Pedestrian Improvements 8th to 31st
- Region-wide Sign Replacement and Pavement Marking projects
New 2024 Construction Projects within PPACG
- Powers/Airport Interchange
- Baptist Road/Terrazzo Roundabout
- I-25 Resurfacing Midway MP 119-124
- US24 Signal Replacements in Woodland Park (Trout Creek and Aspen Garden/Paradise Circle)
- US85/Carson Blvd T Intersection Improvements (continuous green NB)
Planned Future 2025 Construction within PPACG:
- CO115 Resurfacing Nelson Blvd to Brookside
- CO67D North of Woodland Park Improvements – re-AD pending funding
Slide 4
Other CDOT Projects within the Central Front Range Area
Active Construction Projects within CFR
- CO115 Reconstruction MP 27-39 substantial completion by August (El Paso)
- CO9/US285 Reconstruction – Intersection and Bridge (Park)
- CO9 Alma NB and US285 Grant WB Chain Up Stations still waiting on the lighting control centers (Park)
New 2024 Construction Projects within PPACG
- US24G Resurfacing east of Falcon to east of Peyton (El Paso)
- US50 Resurfacing from Salida to Coaldale (Fremont)
- CO115/US50 EB Ramps Roundabout (Fremont)
Planned Future 2025 Construction within CFR:
- US24A Resurfacing Florissant through Divide (Teller)
- US285 Resurfacing through Bailey MP 220-228 (Park)
Slide 5
CDOT Projects within the Pikes Peak Area Council of Governments
Active Construction Projects within PPACG
- MAMSIP I-25 Reconstruction
- I-25: Fillmore to GoG Reconstruction
- ADA Ramp Reconstruction various locations in Fountain, Colorado Springs, Monument & Palmer Lake
- US24 Pedestrian Improvements 8th to 31st
- Region-wide Sign Replacement and Pavement Marking projects
- CO115 Reconstruction MP 27-39 substantial completion by August (CFR)
New 2024 Construction Projects within PPACG
- Powers/Airport Interchange
- Baptist Road/Terrazzo Roundabout
- I-25 Resurfacing Midway MP 119-124
- US24G Resurfacing east of Falcon to east of Peyton (CFR)
- US24 Signal Replacements in Woodland Park (Trout Creek and Aspen Garden/Paradise Circle)
- US85/Carson Blvd T Intersection Improvements (continuous green NB)
Planned Future 2025 Construction within PPACG:
- CO115 Resurfacing Nelson Blvd to Brookside
- CO67D North of Woodland Park Improvements – re-AD pending funding
- US24A Resurfacing Florissant through Divide (CFR)
Slide 6
Other CDOT Projects within the Central Front Range Area
Active Construction Projects within CFR
- CO9/US285 Reconstruction – Intersection and Bridge (Park)
- CO9 Alma NB and US285 Grant WB Chain Up Stations still waiting on the lighting control centers (Park)
New 2024 Construction Projects within PPACG
- US50 Resurfacing from Salida to Coaldale (Fremont)
- CO115/US50 EB Ramps Roundabout (Fremont)
- US24G Resurfacing east of Falcon to east of Peyton
- US24 Signal Replacements in Woodland Park (Trout Creek and Aspen Garden/Paradise Circle)
- US85/Carson Blvd T Intersection Improvements (continuous green NB) (Letting June 6th)
Planned Future 2025 Construction within CFR:
- US285 Resurfacing through Bailey MP 220-228