Board of Directors Workshop – Sept. 6, 2024: Federal Fiscal Year 2024 & Federal Fiscal Year 2025 Unified Planning Work Program Amendment 1 Public Comment Period – Introduction


1.1 Pikes Peak Area Council of Governments

The Pikes Peak Area Council of Governments (PPACG) is a forum for cities, towns, tribal governments, counties, transit agencies, and state agencies to address common regional issues. As the Council of Governments (COG), PPACG provides services to all of El Paso, Park, and Teller Counties. However, within that boundary is a smaller boundary of the Pikes Peak Area Metropolitan Planning Organization (MPO). PPACG also serves as the MPO, that is the regional planning organization that develops policies and makes decisions about transportation planning for the greater Colorado Springs Urban Area.

Figure 1: COG and MPO Boundaries

A map of the three-county region of the Pikes Peak Area Council of Governments

Figure 2: Colorado Springs Metropolitan Planning Area

Boundary map of the Pikes Peak Metropolitan Planning Organization

The State of Colorado is divided into 15 Transportation Planning Regions (TPRs). There are five MPOs in Colorado and their boundaries are the same as TPRs 1 through 5. All other parts of the state not included in an MPO boundary are included in TPRs 6 through 15. TPRs are the mechanism by which the State plans and programs state transportation funding. The PPACG Council of Governments boundary includes the Pikes Peak MPO (TPR 1) and a portion of the Central Front Range Transportation Planning Region (TPR 14). PPACG and the Colorado Department of Transportation (CDOT) work in close coordination to optimize the transportation investments in the area.

This Unified Planning Work Program (UPWP) covers only the Pikes Peak MPO (TPR 1).

Figure 3: Colorado TPRs

A map of the Colorado Transportation Planning Regions

1.2 The MPO and Planning Process

The U.S. Department of Transportation (USDOT) has established policy guidelines to improve regional transportation planning and give local communities a stronger voice in achieving their transportation goals while avoiding duplication of planning efforts.

The planning process provides the information, tools, and community outreach needed to improve transportation system performance. It includes extensive coordination with federal, state, and local agencies, as well as ongoing outreach to stakeholders throughout our planning area.

Federal transportation planning regulations require any urbanized area with a population over 50,000 to form an MPO. If that urbanized area has a population over 200,000, the MPO is recognized as a Transportation Management Area (TMA) and additional federal regulations apply. As an MPO/TMA, PPACG is required to develop a long-range transportation plan (LRTP) and transportation improvement program (TIP) for the Colorado Springs Urbanized Area (UZA).

As the designated MPO for the Pikes Peak region, PPACG is responsible for carrying out a “…continuing, cooperative and comprehensive multimodal transportation planning process, including the development of a metropolitan transportation plan (the Long-Range Transportation Plan or LRTP) and a transportation improvement program (TIP)…” The LRTP and TIP are intended to encourage and promote “the safe and efficient development, management, and operation of surface transportation systems to serve the mobility needs of people and freight (including accessible pedestrian walkways and bicycle transportation facilities) and foster economic growth and development, while minimizing transportation-related fuel consumption and air pollution ” (23 Code of Federal Regulations [CFR] 450.300).

As both the designated MPO and the Air Quality Planning Agency, PPACG is responsible for performing regional air quality conformity analyses and demonstrating regional air quality conformity for carbon monoxide (CO). The boundaries of the metropolitan planning area (Figures 1 and 2) and the air quality planning area (Figure 4) are very similar, but not identical.

Figure 4: Colorado Springs Air Quality Planning Area

A map of the air quality maintenance area in the Pikes Peak region

1.3 Unified Planning Work Program

The UPWP incorporates in one document all federally assisted state, regional, and local transportation planning and transportation-related air quality planning activities proposed to be undertaken in the Colorado Springs Urbanized Area during the federal fiscal years (FFYs) 2024 and 2025, beginning October 1, 2023, and ending September 30, 2025. The UPWP is required as a basis and condition for all federal funding assistance for transportation planning and transportation-related air quality planning by the joint planning regulations of the Federal Highway Administration (FHWA) and the Federal Transit Administration (FTA). This document reflects the PPACG’s goals, the LRTP, and the Memorandum of Agreement (MOA) with PPACG, CDOT and Colorado Springs Mountain Metropolitan Transit (MMT).

This work program was developed to serve these specific objectives:

  1. Define transportation planning activities to meet the transportation needs of local, state, and federal agencies.
  2. Identify funding sources for planning studies.
  3. Coordinate transportation planning activities and relationships (both internal and external).
  4. Promote the wise use of public resources through sound decision-making and interagency coordination.

The revenue utilized for PPACG’s work activities documented in the UPWP originates from federal and non-federal sources (See Section 3). These funds are allocated to work activities in accordance with appropriate regulations and are used to pay for program expenditures by the MPO Transportation Planning Program. Federal planning funds, available from both FHWA (PL funds) and FTA (5303 funds), are administered by CDOT through the Consolidated Planning Grant (CPG) Program. CPG funds are allocated to PPACG on an 82.79 percent federal and 17.21 percent non-federal ratio. Non-federal funds are provided to PPACG from dues paid by its member (local government/jurisdiction) entities, and through grants and other ad hoc funding sources such as in-kind match.

Progress made on planning activities in the UPWP is reported in the PPACG Mid-Year and Year-End Reports. These reports outline activities completed and expenditures by work element on a semi-annual basis. UPWP project progression is tracked and where information is documented. These reports are also made available to the public on the PPACG website under the UPWP section.

1.4 Governance and Organizational Structure

PPACG is led by a Board of Directors composed of elected officials from our member jurisdictions. Membership, officers and voting procedures are in accordance with the Bylaws adopted by the Board of Directors. Standing advisory committees and ad hoc task forces provide the Board with guidance on matters related to funding, congestion management, bicycle and pedestrian issues, intelligent transportation systems, transit, freight, and other specific matters related to transportation planning. The standing committees are the Air Quality Technical Committee, the Community Advisory Committee, the Transportation Advisory Committee, and the Mobility Coordinating Committee.

All MPO transportation planning activities are guided by federal and state regulations and the PPACG Board of Directors.

All MPO activities involve our member jurisdictions, CDOT, FHWA and FTA, other community groups or stakeholders, and the public as required. The Transportation Advisory Committee (TAC) is a group of technical experts representing the jurisdictions within the MPO that provides guidance and recommendations to PPACG staff regarding transportation planning activities. The Community Advisory Committee (CAC) is comprised of members of the public designated by our member jurisdictions, local organizations, and at large per the CAC bylaws. The CAC provides guidance and public perspective on items recommended by the TAC prior to approval by the Board of Directors. MPO activities are formally approved by the Board of Directors.

Figure 5: Organizational Structure

A flowchart of the PPACG organizational structure

The chart shows the PPACG MPO planning in the center, with overlapping circles indicating coordination with other community groups, the public, member jurisdictions, the Colorado Department of Transportation, Federal Highways Administration and the Federal Transit Agency. This MPO planning process then moves into the PPACG committee process, starting with the Transportation Advisory Committee and moving to the Community Advisory Committee and the Board of Directors.

1.4.1 Public Participation and Outreach

Public involvement for individual planning activities such as the TIP and LRTP is sought in accordance with the PPACG Public Participation Plan (PPP) and the individual public involvement plans for those activities.

The PPP outlines PPACG’s approach to community outreach, along with the types of strategies staff will use to reach target audiences. The PPP is designed to facilitate participation by a range of community members, including traditionally under-served groups and individuals including minorities, seniors, low-income populations, and individuals with disabilities. Implementation of the tactics outlined in the Plan will provide an array of opportunities for meaningful public involvement and ensure compliance with all applicable federal regulations. Outreach efforts will be undertaken as necessary in support of transportation planning activities as they occur.