SUMMARY
Pikes Peak Area Council of Governments (PPACG) staff would like to provide an update for the 2050 Long Range Transportation Plan (LRTP) process.
Travel Demand Model and Land Use
PPACG staff has received guidance from the Colorado Department of Transportation (CDOT) to develop a new baseline for the state-required greenhouse gas (GHG) analysis of the Travel Demand Model (TDM). PPACG staff is working to minimize any possible delay of the GHG verification process, Transportation Commission approval, and LRTP schedule.
Draft LRTP Sections for Review
A draft of the table of contents and first several sections of the LRTP is being provided to the PPACG committees for information and review. Your feedback would be greatly appreciated. Draft LRTP Review for Committees
Update on Unfunded Project List
A draft unfunded project list was developed by staff and distributed to the TAC prior to the May TAC meeting. We welcome any additional projects that jurisdictions would like to appear on the unfunded list. Please provide those to PPACG staff by October 31, 2024, for integration into the document.
Overview Status
- Travel Demand Model and Land Use: Working to comply with state GHG guidelines .
- LRTP Public Involvement Assistance: A fifth RTPAC meeting has been delayed slightly but is anticipated for fall to preview open house materials once the draft document is ready.
- Active Transportation Plan: Scheduled for adoption in November: Active Transportation – Pikes Peak Area Council of Governments (ppacg.org)
- Transit Plan and Specialized Transportation Plan: Update from MMT. These documents will be included in the overall LRTP and will be part of the LRTP public comment and adoption schedule. Updates are available online at https://coloradosprings.gov/2050-regional-transit-and-specialized-transit-plans.
- LRTP Development: Staff working on document. Sections of the document are being sent to subject-matter experts/community partners for review.
LRTP Schedule for TAC (subject to change)
- 2023
- October
- Call for projects released
- Review and recommend Vision, Goals, Scoring
- November
- Provide additional guidance on financial information specific to discretionary grants
- Review and adjust Scoring tactics as needed following Board approval
- Land use modeling charrette(s)
- December
- Discretionary grant workshop held and funding added to financial plan
- Project applications/updates due
- October
- 2024
- January
- Project scoring (staff) and review
- Project selection
- Project modeling began
- February – August
- Project evaluation and analysis to include modeling
- Project list adjustment with TAC as needed
- Document development, integration of freight study, active transportation, transit, specialized human services information as needed/available
- Federal lands access workshop
- Greenhouse gas rulemaking process with the state*
- September
- Draft document review, document layout
- Community partner reviews
- October
- Portions of the LRTP to be reviewed by PPACG committees
- PPACG to submit baseline and action plan to CDPHE for verification.
- RTPAC Meeting 5, to preview the public comment period (may be pushed to November as needed)
- November-January
- PPACG GHG report to be reviewed by Transportation Commission (timeline pending results from CDPHE)
- Draft document release for public comment (timeline pending)
- Public comment review (timeline pending)
- TAC/CAC approval of final document (timeline pending)
- Official public hearing (timeline pending)
- Final document adoption (timeline pending)
- LRTP adoption required for region to stay in compliance
- January
Note: The LRTP must be adopted in January in order for the plan to remain compliant; a non-compliant plan will The GHG rulemaking process may cause a shift in the timeline of the LRTP depending on state approval processes and timeframes.
The transit and specialized human services plans are also federally required and will be adopted in line with the LRTP. The active transportation plan does not and may be shifted as makes sense for that project.
PROPOSED MOTION
Information only
ATTACHMENT(S)
None.
STRATEGIC PLAN GOALS
☐ Advocacy: Serve as an effective advocacy voice for common ground issues.
☒ Information Sharing: Serve as a significant resource for PPACG members to collect and share information with regional partners.
☐ Aging: Expand and extend senior access, awareness, education, and connectivity to support age-friendly communities and empower individual seniors.
☒ Transportation: Maintain and improve a coordinated, validated plan for transportation needs across the PPACG region.
☒ Program Excellence: Continue to excel in the key fundamental areas of PPACG: Military support, Environmental programs, Transportation, Area Agency on Aging, and regional communication and collaboration.