Appendix K: Implementation Schedule
Implementation Schedule
Security Sanitation District
River Bend Creek Lift Station
- Permitting
- Submit Site Application Report
- Local Agency Review: June 2024 through September 2024
- CDPHE Site Application Review: September 2024 through November 2024
- CDPHE BDR Review: November 2024 through January 2025
- Submit Site Application Report
- Design
- Final Design (BDR, Plans, and Specs): July 2024 through January 2025
- Construction
- Bidding: February 2025 through March 2025
- Site Construction: April 2025 through June 2025
- Equipment / Electrical: Equipment Lead Time 10-16 weeks, June 2025 through August 2025
- SCADA: August 2025 through September 2025
- Start-up / Certification: September 2025 through October 2025
- Online: October 2025