Appendix I: Preliminary Cost Estimate and Operating Budget

2024 Preliminary Cost Estimate

Client: Avatar Equities, LLC
Project: River Bend Creek Lift Station
Project #: 296.01

Item #Item DescriptionUnitQualityUnit CostAmount
Lift Station
1General Conditionals, MobilizationLS1$122,025.00$122,025.00
2Site WorkLS1$75,000.00$75,000.00
3Base Course SurfacingLS1$25,000.00$25,000.00
47.5 HP Centrifugal PumpEA3$22,500.00$67,500.00
56′ ID Wet Well ManholeLS1$30,000.00$30,000.00
6Odor Control SystemLS1$28,000.00$28,000.00
7GeneratorEA1$75,000.00$75,000.00
8Valves and PipingLS1$40,000.00$40,000.00
9Auxillary Storage (20,000 gal. tank)EA1$125,000.00$125,000.00
10Pre-Cast Grease InterceptorEA1$18,000.00$18,000.00
11Vertical Structure (Approx. 15′ x 20′)EA1$250,000.00$250,000.00
12Vegetation/Erosion Control/LandscapingLS1$30,000.00$30,000.00
14Electrical and Controls*LS1$50,000.00$50,000.00
Lift Station Subtotal$935,525.00
Foremain
154″ PVC – Trench InstallationLF1,500$90.00$135,000.00
16Air/Vac VaultEA1$12,000.00$12,000.00
17Tie-in to Gravity SystemLS1$15,000.00$15,000.00
18Construction SurveyingLS1$4,000.00$4,000.00
Forcemain Subtotal$166,000.00
Subtotal$1,101.525
20% Contingency$220,305
Construction Total$1,321,830

*Developer to supply 3-phase power to site

Annual Operating Budget – Lift Station #1

Item #Item DescriptionMonthly CostAnnual Cost
19Power$210.00$2,520.00
20Labor$783.00$9,396.00
21Repairs$562.50$6,750.00
 Total$1,555.50$18,666.00

Since the Engineer has no control over the cost of labor, materials or equipment, or over the Contractor’s method of determining prices, or over competitive bidding or market conditions, their opinions of probable construction cost provided for herein are made on the basis of their experience and qualifications. These opinions represent their best judgement as a design professional familiar with the construction industry. However, the Engineer cannot and does not guarantee that proposals, bids, or the construction cost will not vary from opinions of probable cost prepared by them.