Appendix K: Implementation Schedule

Implementation Schedule
Security Sanitation District
River Bend Creek Lift Station

  • Permitting
    • Submit Site Application Report
      • Local Agency Review: June 2024 through September 2024
      • CDPHE Site Application Review: September 2024 through November 2024
      • CDPHE BDR Review: November 2024 through January 2025
  • Design
    • Final Design (BDR, Plans, and Specs): July 2024 through January 2025
  • Construction
    • Bidding: February 2025 through March 2025
    • Site Construction: April 2025 through June 2025
    • Equipment / Electrical: Equipment Lead Time 10-16 weeks, June 2025 through August 2025
    • SCADA: August 2025 through September 2025
    • Start-up / Certification: September 2025 through October 2025
    • Online: October 2025