2050 Long Range Transportation Plan: Implementation Plan


The Pikes Peak Region will invest in outcome-driven activities that specifically meet the goals and priorities established in the LRTP. The LRTP utilized qualitative and quantitative data gathered through citizen input, partner agency participation, technical analysis, project scoring, and local engineering expertise to identify the highest priority needs in which to direct funding.

Implementation Strategies

To ensure the transportation system meets existing and future travel needs of the PPACG region, the LRTP includes implementation guidance for maintenance, operations, safety, motorized, nonmotorized, transit, and specialized transportation systems. It should be noted that PPACG does not have the authority to construct projects, maintain infrastructure, or develop policy for the jurisdictions and other transportation organizations in the region.

Roadway

Roadway and highway transportation projects tend to be the focus of investments and improvements for most MPOs nationwide. The projects in this LRTP funded by federal and state dollars are primarily maintenance, operations improvements, congestion management and safety, not construction of new roads or road widening. The construction of new roads within the region is primarily paid for through private funding as part of development agreements. In addition, the PPRTA provides local funds that may be utilized for any type of roadway or other transportation project, including road widening or development. These projects are proposed by the member governments of the PPRTA and are approved by taxpayers; thus, they are not subject to the approval of PPACG or the TC.

The roadway projects recommended for implementation are shown in the fiscally constrained project list, Table 8-1. This table includes all funding streams in order to provide transparency to the public and a more holistic approach to the regional transportation system.

However, the projected funding for the region is not anticipated to fulfill regional needs. Because of this, an unfunded project list is also included in this chapter to identify additional projects that may be considered in the future.

Maintenance

Funding preventive maintenance is crucial to maintaining a transportation system, including maintaining or rehabilitating road surface, and replacing or repairing bridges, as well as maintaining bicycle and pedestrian facilities and public transportation. This is particularly important considering the projected needs resulting from projected regional population increases and economic growth over the life of the plan.

The following strategies are recommended.

  • Continue resurfacing and reconstruction programs, with priority assigned to higher volume routes.
  • When possible, standardize design and use of pavements that better absorb noise and drain water, such as the application of rubberized pavements.

Management and Operations

System management refers to programs and infrastructure that are used to operate roadways. The goal is to make the transportation system as effective and efficient as possible. Some of the most common features include signal synchronization, traffic monitoring, variable message signs, incident management, public information programs, and marked detours.

Transportation System Management and Operations strategies will be considered and analyzed in connection with all investments in the plan either as stand-alone projects or as part of another transportation project.

  • Implement intelligent transportation system (ITS) architecture to enhance incident management program effectiveness.
  • Support real-time traveler-information systems, incident management, and information/communication/monitoring systems, including live video feed or internet access to traffic cameras.
  • Install “pedestrian timing signals” that count down time remaining for pedestrians to cross at major pedestrian intersections. Install audible pedestrian signal equipment at key locations as warranted. Use alternative pedestrian detection and pre-emption systems as appropriate.
  • Expand travel demand management programs to help reduce the number of peak-period single-occupant automobile trips.
  • Better link transportation planning and operations, which may include data or resource sharing, cooperative planning, or operations activities.

Transit

While the fiscally constrained project list in this LRTP includes major transit projects and funding pools, the 2050 Regional Transit Plan (Appendix B) includes a detailed implementation plan and project list that provides detail beyond this LRTP. Implementing the full vision of the Regional Transit Plan would achieve many of the goals of MMT and its stakeholders through the following:

  • Make transit a more competitive travel option, especially along the seven identified enhanced transit corridors.
  • Tailor new service options to demand by introducing innovative mobility zones that can build up transit demand in unproven or growing markets.
  • Improve the transit service for existing riders by increasing frequency and extending service span on all local routes.
  • Increase access to jobs and services by combining some existing routes into new crosstown routes.
  • Serve areas of high existing and expected growth with new local and express transit routes.
  • Sustainably support service expansion with capital investments in new buses, transit centers, a new maintenance facility, and establishing programs within MMT to partner with municipalities to improve the accessibility, comfort, and competitiveness of riding transit in the Pikes Peak Region.

Specialized Transportation

The following five recommended strategies were identified in the 2050 Specialized Transportation Plan, which is included in this plan at Appendix C. These strategies are not fiscally constrained.

  • High-Priority Strategies
    • Incrementally develop a One-Call One-Click center.
    • Coordinate with providers to help secure funding for right-sized, shared, and well-maintained vehicles that meet ridership needs.
    • Commission mobility services under improved standards of service.
  • Medium-Priority Strategies
    • Create a program to reimburse people for Uber, Lyft, and taxi rides in situations where there is a critical unmet transportation need based on the time and location of the trip.
    • Consolidate all resources and explore training options for drivers.

Implementation of these strategies would require coordination among various groups within the Pikes Peak Region and, in some cases, additional funding.

Active Transportation

As noted in Chapter 7, there are multiple funding sources specifically designated for active transportation (bicycle and pedestrian) projects. Specific projects are contained in the fiscally constrained project list, Table 8-1, as well as several additional projects that have active transportation elements. The Active Transportation Plan, adopted in 2024, contains a variety of additional recommendations for the future. Below is a summary list of recommendations from that plan:

  • Adopt a Regional Corridors Network
  • Identify and Pursue Big Lift Projects
  • Reserve Right-of-Way (ROW) in Future Roadway Corridors
  • ADA Transition Plans
  • Complementary Programmatic Projects
  • Develop Regional Design Guidelines
  • Local Programmatic Gaps Identification
  • Update Local Development Review Processes
  • Install Amenities at Strategic Locations in Regional Corridor Network
  • Develop Amenities Brochure for External Investments
  • Explore Operations and Maintenance Agreements
  • Create a Terminology and Consistency Committee
  • Adopt Common Language
  • Adjust Local Ordinances And Policies
  • Create Wayfinding Committee
  • Create Shared Micromobility Committee
  • Consolidate Regional Active Transportation Data

Freight

The Regional Freight Mobility Study’s findings culminated with the identification of projects and corridors designed to improve freight mobility and the position of the region for future population growth and the demand for freight infrastructure.

The study includes the following implementation actions:

  • Continue coordination with regional, state, and federal stakeholders around freight planning implementation activities, such as engagement with the Colorado Freight Advisory Committee and CDOT Freight Mobility and Safety Branch.
  • Build on the region study through development of a freight plan and other specific studies as needed.
  • Consider establishment of a PPACG freight working group.
  • Explore funding programs available through the IIJA relevant to specific freight needs within the region, such as the National Highway Freight Program (NHFL), CRIS), and the Grade Crossing Elimination Program.

Passenger Rail

As previously noted, the FRPR District has been established to plan, design, finance, construct, operate, and maintain a new passenger rail system along the Front Range. Following the development of the SDP to guide implementation, recommendations may be included in future LRTPs as applicable.

Safety

Safety improvements are vital to the regional transportation system in order to reduce the number of crashes, serious injuries, and fatalities in the region. Many of the project in the fiscally constrained list are safety projects or have safety components. In addition, the following strategies are recommended.

  • Continue effective programs to monitor and evaluate the highway system to make it possible to identify locations where improvements are needed. Conduct necessary studies and improve deficient locations.
  • Support CDOT’s efforts to implement the goals, strategies and project needs set forth in the SHSP.
  • Continue to participate in Colorado’s SHSP and provide direct input to its working groups.
  • Conduct and support Safety Action Plans within the region as well as their implementation.
  • Work cooperatively with CDOT and local governments to obtain grant funding such as Safe Routes to Schools, SS4A, and other sources as possible.

Fiscally Constrained Project List

As described in Chapter 2, this LRTP includes a fiscally constrained project list developed to support the LRTP goals in coordination with the local jurisdictions and planning partners. Projects included in Table 8-1 are recommended for implementation from 2025 through 2050. In total, the fiscally constrained project list includes $5.3 billion in projects to be funded over the next 25 years.

These projects are planned to be funded through various sources, including private, local, PPRTA, state, and federal funds. Projects were submitted by the local jurisdictions. They were then evaluated, scored, and prioritized by members of our TAC. The projects represent the regional priorities that can be funded with sources that are reasonably expected to be available throughout the life of the plan. Chapter 7 discusses the expected revenues and costs in detail. Projects in the region must be consistent with this LRTP in order to be eligible for federal funds. However, inclusion in this plan does not guarantee funding or completion.

Projects that have funding programmed in the FY 2025-2029 TIP are considered as part of the fiscally constrained long-range plan revenues and estimates and are included in Table 8-1. However, the TIP is amended as needed. The listing in this document is as of November 6, 2024; the electronic TIP (eTIP) on the PPACG website should be consulted for the most up-to-date TIP information. It should be noted that for transparency the fiscally constrained list contains TIP projects that have funding that was programmed in previous years but has not yet been encumbered in a contract. In line with federal regulations, that funding rolls over on an annual basis. When the funding is committed to a contract, it will be taken out of the TIP. This occurs on an annual basis in line with the end of the state fiscal year.

The fiscally constrained project list (Table 8-1) contains 232 projects throughout the Pikes Peak Region. Although specific funding sources were not identified for each project, the funding sources for these projects are identified in the Financial Plan, Chapter 7. The fiscally constrained project list contains only those transit projects that would fall into those regional funding sources. Additional funding specific to transit or specialized transportation, such as FTA Section 5307 and 5310 funding, are identified in the Regional Transit Plan and Regional Specialized Transportation Plan, respectively, as are projects utilizing that funding.

Table 8-1: Fiscally Constrained Project List

Project SponsorProject IDProject NameProject DescriptionEst. Cost
CDOT2019-144BUILD Grant/MAMSIP: I25 and CO94 Safety ImprovementsMilitary Access, Mobility and Safety Improvement Project (MAMSIP)/BUILD Grant – HSIP, Bridge Asset, water quality, and SB267 funds for years 2020, 2021 and 2022 for Charter Oak, South Academy, I25 Safety Improvements, and CO94 Improvements included in BUILD grant project. State match is in the project from multiple state funding pools.$436,227
CDOT2050-001CDOT 10 Year Plan Transit Projects 1068, 2556, 2763New Regional Fixed-Route Transit Service in Teller County, Mountain Metropolitan Transit Fixed-Route Service Expansion – Stage 1, Academy Boulevard/Hancock Expressway Transfer Center. $8,400,000
CDOT2023-048CO105A Palmer Lake RehabilitationPre-construction activities for long-term rehabilitation of CO105A near Palmer Park to address issues with pavement deterioration and groundwater$100,000
CDOT2050-002CO16 Safety and Operational ImprovementsScope to be determined.$60,000,000
CDOT2025-005CO21 and Grinnell Blvd Drainage RepairsPrograms funds for urgent/emergency safety repairs on a failing culvert on CO21.$400,000
CDOT2023-034CO21 (South Powers) Median BarrierMedian barrier on CO21/South Powers Blvd.$197,000
CDOT2022-001CO21 and Airport Rd Diverging Diamond InterchangeCO21 (Powers Blvd.) and Airport Road Interchange Design.$6,520,140
CDOT2050-003CO21 EA Corridor ManagementScope to be determined per the environmental assessment.$2,250,000
CDOT2022-019CO21 Grade Separated Interchange at Milton E. Proby ParkwayNew interchange.$92,900,000
CDOT2050-004CO21A and B Safety and Operational ImprovementsScope to be determined.$4,000,000
CDOT2050-005CO21B/Dublin InterchangeNew Interchange.$68,000,000
CDOT2050-006CO21B/Stetson Hills InterchangeNew Interchange.$71,000,000
CDOT2019-122CO83 Passing Lane between CO105 and Palmer Divide RdCO83 passing lanes safety project MP 28 – MP 30.$5,000,000
CDOT2050-007CO83 Roundabout at Palmer Divide RdScope to be determined$10,100,000
CDOT2025-008CO83A & County Line Rd Intersection ImprovementsReplace existing temporary span wire signal and with full mast arm signal and upgrade existing signal equipment at the intersection of CO83A and County Line Rd. Work may potentially include minor intersection improvements to add acceleration and/or deceleration lanes.$1,100,892
CDOT2050-008CO94 Widening and Safety ImprovementsWidening highway and shoulders for safety.  2+1 will maintain two through lanes with +1 providing improved auxiliary and turn lanes.  Budget is insufficient for the entire project area.$25,000,000
CDOT2019-120I25 Filmore to Garden of the GodsI25 Fillmore to Garden of the Gods bridge repairs and surface treatment.$4,202,864
CDOT2050-009I25 Cimarron-N Nevada WideningInterstate widening and capacity improvement to accommodate an additional lane expected to be an HOV (possible TEL operation as well).$137,500,000
CDOT2050-010I25 EA Corridor ManagementScope to be determined.$1,250,000
CDOT2050-011I25 Exit 125 (Ray Nixon) Interchange Operations and Safety Improvements (S Powers connection, RR, industrial)Non-capacity safety and operational improvements, including potential auxiliary lanes, shoulder widening, and bridge replacement.$30,900,000
CDOT2023-049I25 Midway NorthCDOT Region 2 rehabilitating I25 from MP 119 to MP 125.$4,745,493
CDOT2050-012I25 Safety and Operational ImprovementsScope to be determined. Includes an existing TIP project at Exit 135 South Academy to Exit 138 Circle/Lake.$32,000,000
CDOT2050-013I25: S Academy-Circle Safety and Operational ImprovementsNon-capacity safety and operational improvements, including potential auxiliary lanes, shoulder widening, water quality and drainage improvements, and bridge replacement.$48,700,000
CDOT2050-014MLOS ActivitiesAsset management (maintenance levels of service).$398,800,000
CDOT2022-002Mobility/Safety Improvements SH 21, MM 132-154Design funding for mobility or safety improvements along the corridor within the limits of MM 132-154.$400,000
CDOT2050-015PP Area BTE Bridge ReplacementsPikes Peak area Statewide Bridge and Tunnel Enterprise (BTE or Enterprise).$83,600,000
CDOT2050-016PP Area Culverts, Walls, Other AssetsScope to be determined.$11,000,000
CDOT2050-017PP Area Resurfacing & Bridge RehabScope to be determined.$378,600,000
CDOT2050-018PP Area Safety ImprovementsScope to be determined.$100,000,000
CDOT2050-019PP Area Signal ReplacementScope to be determined.$15,000,000
CDOT2050-020PP Area Transit, Multi-modal and Technology ImprovementsScope to be determined.$124,100,000
CDOT2023-015SH115 – Nelson Blvd to I25 Improvements ProjectThe project will consist of resurfacing of the existing roadway. The project limits are along CO115 from approximate MP 41.7 to MP 47.5. In addition to pavement resurfacing on the roadway, key elements of the work on this project include guardrail replacement and modification, ADA curb ramp rehabilitation and replacement, re-striping, safety improvements, and temporary erosion control. $15,665,000
CDOT2022-010US24G Falcon Hwy to West of Elbert Rd.US24G Falcon Hwy to West of Elbert Rd. surface treatment.$5,739,106
CDOT2023-032US24 Falcon- Judge Orr Intersection ImprovementsImprovements to the Intersection of US24 and Judge Orr Road in Falcon.$8,759,000
CDOT2022-005US24 West over Ridge RoadNon-capacity grade separation and access modification of US24A and Ridge Rd.$33,000,000
CDOT2050-021US24A BTE Bridge Replacements (incl. I-17-GD/E)Scope to be determined.$8,250,000
CDOT2050-022US24A EA Corridor ManagementScope to be determined.$1,200,000
CDOT2050-023US24A Safety & Operational ImprovementsScope to be determined.$15,500,000
CDOT2050-024US24A/21st Interchange Phase 1This project is for preconstruction work only to investigate a new interchange per the EA. Budget is insufficient for the entire project area, so this will constitute phase 1 including planning, design and ROW acquisition.$77,000,000
CDOT2050-025US24A/26th Intersection ImprovementsNon-capacity intersection improvements.$3,000,000
CDOT2050-026US24A/31st Intersection ImprovementsNon-capacity intersection improvements in accordance with the EA.$22,500,000
CDOT2021-047US24G Safety and Operational ImprovementsScope to be determined.$6,800,000
CDOT2050-027US24G Widening Garrett-WoodmenWidening the highway from 2 to 4 lanes total, or additional auxiliary and other lanes to achieve lane balance and decreased delay. Includes intersection and access improvements, including a likely frontage or backage road parallel to US24G from Garrett to Falcon Hwy. Includes design funding in the TIP.$67,500,000
CDOT2050-028US24G Widening Woodmen-StapletonWidening the highway from 2 to 4-lanes total, or additional auxiliary and other lanes to achieve lane balance and decreased delay.$71,000,000
CDOT2050-029US24H Rehab and ReconstructionNon-capacity safety, operations, shoulder improvements, and resurfacing of the highway.$18,800,000
CDOT2050-030US85 BTE Bridge Replacements (incl. J-18-M)Scope to be determined.$19,800,000
CDOT2050-031US85 Safety and Operational ImprovementsScope to be determined.$14,000,000
CDOT2022-006Woodland Park Reliever Route StudyStudy to investigate the possibility of a reliever route and potential alignments.$500,000
Colorado Springs2050-03230th St Corridor Improvements – Mesa Rd to Garden of the Gods RdConstruct paved shoulders, drainage, and intersection improvements along 30th St from Mesa Rd to Garden of the Gods Rd.$21,300,000
Colorado Springs2045-24731st St/Camp Creek Roadway and Trail Improvements – Kiowa St to Fontanero StReconstruct roadway and bridges along the corridor to accommodate conversion of the concrete channel to a naturalistic rock lined channel. Includes new off-street trail and wayfinding signage for the corridor.$30,000,000
Colorado Springs2021-00131st Street and Fontanero Bridge ReconstructionStudy to investigate the possibility of a reliever route and potential alignments.$5,749,525
Colorado Springs2045-0578th Street Improvements – US24 to Fountain CreekConstruct roadway, pedestrian, and bicycle improvements and a bridge replacement at Fountain Creek.$16,579,260
Colorado Springs2025-005Academy Bridge over PlatteReplace Academy bridge over Platte Ave in configuration that better accommodates pedestrian movements along Academy and access to transit, and conversion to quadrant road interchange.$17,580,000
Colorado Springs2045-241Austin Bluffs Pkwy/Garden of the Gods Rd./Nevada Ave. Intersection Improvements and Bridge ReplacementThis project will improve traffic operations, multimodal access and safety for the intersection of Austin Bluffs Parkway/Garden of the Gods Road and Nevada Avenue. The intersection will be designed based on the PPRTA3 Intersection Study. The project will also require a new bridge on Garden of the Gods Road over Monument Creek due to condition issues and to accommodate new configuration.  The project includes extension of the multi-use trail along Austin Bluffs Parkway to the Pikes Peak Greenway and considers future enhanced transit connections along Nevada Ave.$15,000,000
Colorado Springs2050-033Campus to Campus CorridorEnhanced Transit Corridor including Mobility Hubs connecting Pikes Peak State College Transfer Centers (at South Academy Blvd and Interquest Pkwy) to USAFA Gateway Visitor Center. Routing generally following Academy Blvd, Voyager Pkwy, and Northgate Blvd as determined by further analysis.$8,000,000
Colorado Springs2050-034Cascade Ave – Mark Dabling Connection (construction)Extend Cascade Ave to the north to connect to Mark Dabling Blvd with two new bridges.$52,581,350
Colorado Springs2050-035Cascade Ave – Mark Dabling Blvd Connection (design)Extend Cascade Ave to the north to connect to Mark Dabling Blvd with two new bridges.$3,500,000
Colorado Springs2050-036Circle/Platte Intersection EnhancementsDesign and construct intersection enhancements at the Platte Ave/Circle Dr intersection to address intersection delay and safety.$12,300,000
Colorado Springs2025-010City of Colorado Springs Safety Signal RebuildsRebuild of 6 existing span wire signals to mast arm signals. There rebuilds will include upgrades to improve safety at the intersections. Upgrades would vary per location but would generally include backplates, protected left turn signal phasing, pedestrian crossings, upgrade ramps to PROWAG standards, directional push buttons, countdown heads, and intersection lighting.$2,100,000
Colorado Springs2045-074Colorado Ave. Roadway ImprovementsReconstruct Colorado Ave to improve safety including arterial street traffic calming and enhanced pedestrian crossings. Increase on-street parking, widen sidewalks, and enhance bike/ped wayfinding throughout the corridor.$16,600,000
Colorado Springs2050-037Colorado Avenue Improvements –  Limit St to I25From 8th St to Walnut St, reconstruct the area between the property line and the curb for parking and sidewalk modifications. Add pedestrian mid-block crossings, median landscaping, and bike/ped wayfinding throughout the corridor.$6,000,000
Colorado Springs2045-094Colorado Springs Bridge FundTo provide program funds for bridge replacement, reconstruction or rehabilitation based on needs identified through the City’s Bridge Management Program or emergency condition.$250,000,000
Colorado Springs2045-075Colorado Springs Citywide Congestion and Incident Management Signal ImprovementImplement citywide/regionwide ITS to improve traffic operations, coordinate systems and improve safety. Improvements may include monitoring systems, hardware and software, message systems, metering, communication infrastructure, specialized equipment and staff.$10,000,000
Colorado Springs2045-077Colorado Springs Citywide Intersection ImprovementsConstruct improvements at intersections that will reduce delay, improve air quality, and enhance safety for both motorized and non-motorized traffic.$20,000,000
Colorado Springs2045-080Colorado Springs Citywide On-Street Bikeway ImprovementsProposed bikeway improvements will include: improve and construct bike lanes in accordance with the ITP and the City’s Bicycle Plan; install on-street bicycle lanes and connections to off-street facilities to close gaps on the existing bike network; improve connections from on-street bike lanes to the Colorado Springs trail system and residential/commercial centers; and, develop/implement improved signage to provide better wayfinding for cyclists.$10,000,000
Colorado Springs2045-084Colorado Springs Citywide Roadway Safety and Traffic OperationsThis capital program includes analysis, study, engineering and construction of intersection and corridor “spot” improvements to mitigate existing safety and traffic flow deficiencies. Proposed projects of this type will include the construction of traffic signals, roundabouts, auxiliary traffic lanes, traffic calming features, incorporation of multimodal enhancements, and other lower-cost geometric improvements. These projects may also install guard rail, construct/reconstruct medians, and install traffic control devices where warranted to improve traffic operations and safety.$25,000,000
Colorado Springs2045-081Colorado Springs Citywide Sidewalk Infill ImprovementsProposed pedestrian improvements will continue to construct missing pedestrian connections along transportation facilities, schools, and neighborhoods and will follow the Operations and Maintenance Division quadrant approach to improve safety and develop/implement improved pedestrian connectivity.$20,000,000
Colorado Springs2045-088Colorado Springs Citywide Traffic Signal System UpgradeDesign and reconstruct traffic signal systems across the City to modern signal standards.$25,000,000
Colorado Springs2050-038Colorado Springs Railroad Bridges ProgramRepair/Rehabilitation/Replacement of railroad bridges due to condition issues (such as Uintah, Tejon, Nevada, Shooks Run) or for City required changes to accommodate other improvements.$100,000,000
Colorado Springs2045-090Companion Drainage Improvements for Roadway ProjectsThis program constructs drainage improvements needed in advance of roadway rehabilitation or reconstruction efforts.$10,000,000
Colorado Springs2045-122Costilla and Cucharras St. Improvements over Shooks RunImprove Costilla St. and Cucharras St, including replacing the bridge over Shooks Run and improvements at Nevada Ave, Weber St, Corona St, Prospect St, Institute St, and Cedar St intersections.$10,000,000
Colorado Springs2050-039Cottonwood Creek Trail Corridor Improvements – Union crossingDesign and construct a grade-separated crossing of Cottonwood Creek Trail at Union Blvd.$4,000,000
Colorado Springs2050-040Drennan Rd Bridge over Jimmy Camp CreekReplace bridge due to condition issue.$11,700,000
Colorado Springs2050-041Dublin Blvd Improvements – Peterson Rd to Marksheffel RdReconstruct/construct roadway to widen for appropriate lane configuration and consistent cross section. Project includes bike and pedestrian accommodations.$16,600,000
Colorado Springs2050-042Fillmore Pedestrian Safety ImprovementsConduct a pedestrian safety study along Fillmore St and implement recommendations. Consider access management, access to transit, and safe crossings.$15,000,000
Colorado Springs2045-243/2025-006Fillmore St. Roadway ImprovementsThe bridges over Monument Creek/Pikes Peak Greenway and bridges over the Union Pacific Railroad will be replaced due to condition. The project also includes a trail connection down to the Pikes Peak Greenway. The project will improve the existing sidewalks and pedestrian facilities and widen Fillmore St. from 4 to 6 lanes from Cascade to I25.$117,189,000
Colorado Springs2050-043Foothills Trail ImprovementsTrail program to extend, realign, widen, reconstruct, and construct trails, access to trails, connections to attractions or other portions of the trail network, crossings, wayfinding, ADA improvements and other functional enhancements. May entail engineering, land procurement and construction activities.$500,000
Colorado Springs2022-022Garden of the Gods Rd Intersection Improvements (4 Locations)Safety project to improve intersections on Garden of the Gods Rd at Hilton Pkwy, Northpark, and Mark Dabling. Hilton Pkwy will be reconstructed to restrict the access on the north leg to right-in/right-out, while the south leg will allow 3/4 movement with no outbound left-turns. The westbound left-turn will be protected with a signal that controls westbound left/eastbound through movements. The access east of Hilton Parkway will be reconstructed as right-in/right-out only on both the north and south legs. The median will be reconstructed to extend the I25 eastbound left-turn storage. The Northpark signal will be rebuilt with mast arms, additional through heads, backplates, and fully protected eastbound and westbound left-turns. The Mark Dabling signal will be rebuilt with mast arms, additional through heads, backplates, and flashing yellow arrow eastbound and westbound protected/permissive left-turns.$1,685,933
Colorado Springs2050-044Hancock Corridor Study and ImplementationConduct a study to determine the desired function/role of Hancock Expwy between the airport and Downtown Colorado Springs considering vehicles use, enhanced transit corridor, bike and pedestrian connections, and desired land use$15,000,000
Colorado Springs2050-045Hancock over Sand CreekReplace bridge over Sand Creek due to poor condition.$20,000,000
Colorado Springs2050-046Homestead Trail ImprovementsTrail program to extend, realign, widen, reconstruct, and construct trails, access to trails, connections to attractions or other portions of the trail network, crossings, wayfinding, ADA improvements and other functional enhancements. May entail engineering, land procurement and construction activities.$1,000,000
Colorado Springs2022-013Lake Ave Safety Improvements: CO115 and Southgate RdThe project will modify the existing intersection to include fully protected left turns from all 4 approaches including restripe of eastbound left turn lanes for double left movements and widening of the north leg of the intersection to include 2 receiving lanes.$3,974,334
Colorado Springs2050-047Las Vegas St Bridge over Shooks RunReplace bridge over Shooks Run and provide roadway, intersection and bicycle and pedestrian improvements to address safety, drainage, and access improvements$15,000,000
Colorado Springs2050-048Lorraine St Bridge over Cheyenne RunReplace bridge due to condition issue.$5,000,000
Colorado Springs2050-049Marksheffel Rd Bridge at Cottonwood CreekConstruct bridge crossing of Cottonwood Creek to carry Marksheffel Rd.$27,850,000
Colorado Springs2050-050Midland Trail Completion (21st St to 25th St)Complete the Midland Trail as an off-street facility from 21st St to 25th St.$1,025,000
Colorado Springs2050-051Nevada Ave Reconstruction – Rock Island Railroad to Eagle Rock Rd, Commerce St to Templeton Gap Floodway, Templeton Gap Floodway to Lee St, and Lee St to University VillageReconstruct Nevada Ave to improve vehicular operations at signalized intersections and provide improved transit, bicycle and pedestrian infrastructure to support the N Nevada Redevelopment vision.$103,667,000
Colorado Springs2050-052Nevada Ave/Garden of the Gods Rd/Austin Bluffs Pkwy Intersection StudyConduct an intersection improvement and selection study to identify improvements to the Nevada Ave/Garden of the Gods Rd/Austin Bluffs Pkwy Intersection.$1,000,000
Colorado Springs2050-053Northeast Sub-Area Study – Bounded by Union Blvd, Austin Bluffs Pkwy and Briargate PkwyConduct a multimodal area study to examine the existing functionality of Union Blvd and Austin Bluffs Pkwy from their intersection north to Briargate Pkwy including how this network may better serve traffic demands, local bus, enhanced transit, bikes, and pedestrians. Examine traffic hot spots including major intersections for recommendations on reducing delay and enhancing safety. Identify specific improvements for roadway, transit, and completion of bike and pedestrian network connections.$1,100,000
Colorado Springs2045-249Old Ranch Rd: Voyager Pkwy to Kettle CreekConstruct roadway and drainage improvements to bring Old Ranch Rd to a 5-lane City standard roadway including bike and pedestrian facilities.$19,400,000
Colorado Springs2050-054Palmer-Mesa Trail ImprovementsTrail program to extend, realign, widen, reconstruct, and construct trails, access to trails, connections to attractions or other portions of the trail network, crossings, wayfinding, ADA improvements and other functional enhancements. May entail engineering, land procurement and construction activities.$500,000
Colorado Springs2050-055Pikes Peak Greenway ImprovementsTrail program to extend, realign, widen, reconstruct, and construct trails, access to trails, connections to attractions or other portions of the trail network, crossings, wayfinding, ADA improvements and other functional enhancements. May entail engineering, land procurement and construction activities.$2,000,000
Colorado Springs2050-056Pine Creek Trail Connection – Pikes Peak Greenway to Research PkwyConstruct a shared use path along Pine Creek between Pikes Peak Greenway and Research Pkwy.$3,000,000
Colorado Springs2050-057Plains to Peak CorridorEnhanced Transit Corridor including Mobility Hubs connecting Manitou Springs to Falcon. Routing generally following Colorado Ave, Pikes Peak Ave, Platte Ave, and US24 as determined by further analysis.$4,800,000
Colorado Springs2050-058Platte Ave Improvements – Wahsatch Ave to Circle DrOperational and condition improvements including the Union intersection, bridges and retaining walls.$36,000,000
Colorado Springs2050-059Platte Ave/Academy Blvd Interchange ConversionReconstruct Academy Blvd/Platte Ave interchange to be a quadrant road interchange to facilitate pedestrian movements along Platte Ave by removing ramps and across Academy by eliminating left turns on the bridge.$10,000,000
Colorado Springs2045-160Platte Ave Corridor Improvements – Chelton to PowersConstruct six lane roadway and include a shared use trail, adjacent to Platte Ave between Chelton Rd and Powers Blvd, including connections to existing Sand Creek Trail.$28,300,000
Colorado Springs2045-117Replace and Upgrade Transit IT Equipment and softwareMaintain and upgrade existing transit hardware and software allowing for smart-cards, real-time bus information, traffic signal prioritization, etc. to improve efficiency and customer service.$2,590,000
Colorado Springs2050-060Rock Island Trail Corridor Improvements – Academy Grade SeparationDesign and construct grade-separated crossing of Rock Island Trail at Academy Blvd.$10,000,000
Colorado Springs2025-011Safe Streets 4 All (SS4A) Action PlanDevelop a city-wide safety action plan by engaging stakeholders and by evaluating a wide range of strategies and collaboration to reduce fatal and serious crashes.$350,000
Colorado Springs2025-013Safe Streets 4 All (SS4A) Demonstration ProjectsFive types of demonstration projects will be temporarily installed and before and after data will be evaluated to determine effectiveness. Demonstration projects include rubberized pinned down raised crosswalks, dynamic speed feedback signs, neighborhood pop-up traffic circles, speed activated flashing school zone signs, and projected bike lanes.$1,310,600
Colorado Springs2050-061Shooks Run Trail ImprovementsTrail program to extend, realign, widen, reconstruct, and construct trails, access to trails, connections to attractions or other portions of the trail network, crossings, wayfinding, ADA improvements and other functional enhancements. May entail engineering, land procurement and construction activities.$4,000,000
Colorado Springs2050-062Sinton Trail ImprovementsTrail program to extend, realign, widen, reconstruct, and construct trails, access to trails, connections to attractions or other portions of the trail network, crossings, wayfinding, ADA improvements and other functional enhancements. May entail engineering, land procurement and construction activities.$500,000
Colorado Springs2025-009Strengthening Mobility and Revolutionizing Transportation (SMART)Development and implementation of a multi-dimensional Perception-Based Adaptive Traffic Management and Data Sharing system to address critical real-world challenges in traffic management, including improving safety, reducing congestion, and enhancing the efficiency of transportation systems across urban, suburban, and rural contexts.$14,788,590
Colorado Springs2050-063Templeton Gap Trail ImprovementsTrail program to extend, realign, widen, reconstruct, and construct trails, access to trails, connections to attractions or other portions of the trail network, crossings, wayfinding, ADA improvements and other functional enhancements. May entail engineering, land procurement and construction activities.$500,000
Colorado Springs2050-064Terminal Southgate Enhanced Transit Corridor Study and ImplementationEvaluate options for implementing enhanced transit, options should include routing and operations, and alternate routing.$2,000,000
Colorado Springs2045-098Transit Fleet SupplementFund replacement and expansion transit service vehicle purchases: diesel, gasoline, and any low or zero emission vehicles including supporting infrastructure technologies to fuel and charge.$31,420,000
Colorado Springs2045-
Transit-SP16
Transit Service EnhancementsStudies (including Comprehensive Operation Analysis, Alternate Transportation Implementation Study and other studies) and implementation to improve operations and/or to provide service extension/expansion enhancements to Military Bases, Major Employers, and Tourism Hubs and underserved areas. This program aims to bring public transit in the Colorado Springs area to a higher level by providing direct, frequent, efficient, and reliable transit solutions that continue to focus on improving the existing service area, advancing high-frequency core transit corridors to create improved mobility options for the entire community, improving service hours and frequencies, and implementing new and advanced technologies to improve reliability and advance fleet upgrades.$8,000,000
Colorado Springs2045-
Transit-SP20
Transit Stop and Station ImprovementsNew or existing transit stops and stations; stop improvements could include, but not limited to, safety improvements, customer access, sidewalk connections, ADA-compliance, pre-board fare payment infrastructure, wayfinding, service kiosk, message boards, benches, trash receptacles, and shelters. Station examples include new/relocated stations or transfer centers at Chapel Hills Mall, Citadel Mall, Hancock/Academy, PPSC and other Multimodal Hubs to support ConnectCOS Transit Vision Network including but not limited to Garden of the Gods Rd, PPSC, military bases, downtown and park and rides, and active transportation connections.$10,000,000
Colorado Springs2025-012Uncontrolled Trail Crossing EnhancementsTrail crossing improvements at 8 locations to reduce risk for vulnerable users. Improvements include RRFBs, pedestrian refuge islands, raised crosswalks, signs and markings.$715,000
Colorado Springs2025-003Union Blvd Urban Trail: MLK Bypass to Fountain BlvdConstruct an 8 foot multiuse urban trail from the MLK Bypass eastbound ramp terminus north to Fountain Blvd. The proposed project will extend to the Fountain Blvd sidewalks and planned on-street bike lanes, all withing the existing ROW.$1,490,640
Colorado Springs2050-065US24 Functionality and Routing Study – I25 to FalconConduct a major transportation corridor study to determine safety, traffic operations, transit operations, and functionality of US24 from Falcon to I25 Analyze the function of US24 in the region’s transportation network and consider alternatives for US24 such as Woodmen Rd to meet long-term needs$2,500,000
Colorado Springs2050-066Vermijo Streetscape Improvements – Tejon St to Shooks RunReconstruct roadway to enhance streetscape similar to recent improvements west of Tejon St.$22,500,000
Colorado Springs2023-046Water Street and 31st Street Bridge ReplacementBridge replacement with two concrete box culvert bridges including 460 feet of roadway and channel reconstruction. The project includes a 12-foot trail section as part of an overall plan to improve bicycle and pedestrian safety.$5,000,000
Colorado Springs2045-157Weber St. Transportation ImprovementsImprove Weber St to meet city standards from Lilac St to Jackson St. The project will also construct a trail and transit only connection across the old Rock Island Railroad to Fillmore St. The trail and transit connection includes a bridge and trail connections to the Rock Island Trail.$10,000,000
Colorado Springs2050-067Woodmen/I25 Interchange Congestion ManagementConduct interchange study for Woodmen Rd at I25 to reduce delay and improve safety.$1,000,000
Colorado Springs – MMT2022-017Downtown Shuttle Operations (Service Expansion)Three years of operational support (funding) for the Downtown Shuttle. This transit expansion will serve the downtown core of Colorado Springs, connecting customers to numerous destinations and attractions, while easing traffic congestion.$9,683,318
Colorado Springs – MMT2023-006MMT Metro RidesTravel demand management programs and operations to support congestion relief and mobility choice.$2,327,848
Colorado Springs – MMT2019-088MMT OperatingMMT (Operating, Maintenance, Transit Improvements, Safety & Security).$26,585,945
Colorado Springs – MMT2019-089MMT PlanningMMT planning projects.$1,623,011
Colorado Springs – MMT2019-045MMT Transit Planning StudiesTransit planning studies.$1,345,097
Colorado Springs – MMT2019-091MMT Vehicle PurchasePurchase up to nine hybrid transit vehicles, with MMT committing local match funds.$19,906,966
Colorado Springs – MMT2023-023Two Battery Electric Buses for Service ExpansionAcquire two BEBs and charging infrastructure for service expansion.$3,224,000
El Paso County Public Works2045-244Academy Blvd WideningDesign and construct a road widening from 4 to 6 lanes from I25 ramps to CO115 to include shoulders, improved sight distance with horizontal and vertical improvements, and address turn lanes and intersection improvements where needed. To accommodate the new lanes and multiuse shoulders for enhanced multimodal safety and improve drainage, replace or repair the seven bridges and underpasses to PPSC, and evaluate an interchange at Venetucci Blvd. Evaluate and construct improvements needed to meet current ADA standards.$110,000,000
El Paso County Public Works2045-165ADA Compliance ProgramWork will occur on a variety of roads in the unincorporated area within the MPO boundary to carry out an ADA Compliance Program. Design and construct ADA improvements, missing sidewalk/trail connections, and intersection, signal and signing improvements. $5,000,000
El Paso County Public Works2050-068B Street ImprovementsThis was a project identified in our Local Road Safety Plan as a high crash are that needed safety improvements. Design and reconstruct/construct roadway for appropriate lane configuration which may include pavement overlay, intersection and drainage improvements, transit accommodations, ADA improvements and consistent cross section including multimodal accommodations and access control.$10,000,000
El Paso County Public Works2050-069Baptist/Hodgen/Roller Coaster IntersectionConstruct improvements at the intersection that will reduce delay and enhance safety for both motorized and non-motorized traffic.$8,200,000
El Paso County Public Works2045-169Black Forest Rd: Paving from Walker to County LineDesign and construct surface improvements to Black Forest Rd by converting the gravel road to pavement, fixing alignments, improving drainage, and improving intersections. Evaluate and construct improvements needed to meet current ADA standards.$13,500,000
El Paso County Public Works2050-070Blaney/Davis/Hoofbeat Gravel Road ConversionDesign and construction of a gravel road conversion for freight service. This project supports the regional use of the landfill on Blaney Rd.  These connector roads are gravel and have too many truck trips to safely function for freight.  The gravel roads need to be paved and brought up to current standards including multiuse shoulders, safety improvements, turn lanes and auxiliary lanes, intersection, drainage and water quality improvements. $24,000,000
El Paso County Public Works2045-234Bradley Rd from Goldfield to Powers BlvdConstruct new roadway connection, drainage, upgrade traffic signal, and multimodal features.$23,000,000
El Paso County Public Works2045-245Bradley Rd WideningDesign and construct upgrades on approximately 1 mile of Bradley Rd from Academy to Hancock from two to four lanes and improve sight distance and intersections where needed. From Academy Rd to Hancock Exp. design and construct two additional lanes to improve the road to a four-lane principle arterial with multimodal access and turn lanes where needed. Resurface the current two-lane section and ensure proper drainage. Evaluate and construct improvements needed to meet current ADA standards.$19,200,000
El Paso County Public Works2045-233Bradley Rd: Grinnell to Wageman DrDesign and construct 2 additional lanes and add multimodal features.$24,000,000
El Paso County Public Works2050-071Burgess and Vollmer Intersection ImprovementsBurgess and Vollmer Road Intersection is currently a non-signalized intersection in the Black Forest area, with stop controls on Burgess  Road.  The intersection is currently two-lane rural roadway without turn bays or acceleration lanes. Roadside ditches were graded to convey surface runoff on both side of the road.  There is a need for a safe trail crossing to convey non-motorized traffic between the Black Forest Section 16 Open Space trail, Sand Creek Trail and the proposed Bike Route on Burgess. This project will improve this intersection to a safer operating intersection (options being studied during design are standard signalized intersection or roundabout) and provide a safer ADA compliant trail connection. Also included surface and drainage improvements, signage, striping and road resurfacing if needed.$10,000,000
El Paso County Public Works2045-174Curtis Rd ImprovementsDesign and reconstruct the road segments between Falcon Hwy and CO94. Design and construct features that address the higher accident rate including shoulders and improving sight distance with horizontal and vertical improvements, include drainage features, and add turn lanes and intersection improvements where needed. Add multimodal improvements. Maintain bridges and culverts on this segment. Evaluate and construct improvements needed to meet current ADA standards.$35,000,000
El Paso County Public Works2050-072Eastonville Rd from McLaughlin Rd to BandaneroReconstruct/construct roadway for appropriate lane configuration, intersection and drainage improvements and consistent cross section including multimodal accommodations.$15,000,000
El Paso County Public Works2045-176Eastonville Rd: McLaughlin Rd to EvansDesign and construct surface improvements to Eastonville Rd by bringing arterial roadway to current standards, sight distance, horizontal and vertical improvements, surface paving (existing gravel areas), shoulders, drainage and intersection improvements, auxiliary lane improvements, multimodal improvements.  Evaluate and construct improvements needed to meet current ADA standards.$47,000,000
El Paso County Public Works2021-033El Paso County ADA Inventory and ADA ImprovementsEl Paso County ADA inventory and ADA improvements. EPC is completing an inventory of ROW infrastructure for ADA compliance. This application is for funding to measure ADA attributes to determine if they are compliant and to prioritize and plan for improvements. With this funding request, we will be working on a variety of roads in the unincorporated area within the MPO boundary to carry out an ADA Compliance Program. Projects will include, repair/install sidewalk, repair/install curb cuts, pedestrian crossing improvements/signals, barrier removal, etc. While we realize that minor design, ROW or clearances may be needed at limited locations, our goal is to focus on construction in existing ROW.Project received toll credits and additional federal funding to cover some of the local match requirements.$2,125,632
El Paso County Public Works2019-015El Paso County Wetland Bank: Akers DrDesign and construction of approximately 20 acres of mitigation for inclusion in the El Paso County Wetland Umbrella Mitigation Bank.$1,760,893
El Paso County Public Works2050-073Evans Rd Gravel Road Conversion – Meridian Rd to Elbert RdThis gravel road segment has too many trips to safely function.  The gravel road needs to be paved and brought up to current standards.  The project will design and construct a gravel road conversion to paved roads with multiuse shoulders, safety improvements, turn lanes and auxiliary lanes, intersection and drainage and water quality improvements. $5,000,000
El Paso County Public Works2045-183Fountain Mesa Rd: Caballero Ave to Fontaine Blvd ImprovementsResurface and maintain the road segments, shoulders improvements, pedestrian improvements, improve sight distance, drainage, turn lanes and intersections where needed.$9,000,000
El Paso County Public Works2045-184/2021-009Galley Rd SidewalksDesign and construct missing multimodal segments, upgrade to current ADA standards, and improve intersection safety. Fix the drainage problems.$5,600,294
El Paso County Public Works2045-185Garrett Rd Upgrade: US24 to Curtis RdUpgrade Garrett Rd from US24 to Curtis Rd from a collector to a minor arterial. Resurface and maintain the road segments. Design and construct shoulders, improve sight distance with horizontal and vertical improvements, address drainage, add turn lanes and intersection improvements where needed.$28,000,000
El Paso County Public Works2045-188Hancock Expwy at Clearview Dr/Yucatan DrTraffic signal replacement and intersection reconstruction/safety improvement. Replace signal equipment, auxiliary lane improvements, drainage improvements and pedestrian improvements.$750,000
El Paso County Public Works2045-209CO105 – Furrow Rd to CO83Construct paved multiuse shoulders, improve driving surface, drainage, turn lanes, accel. and decel. lanes, and intersection improvements.$50,000,000
El Paso County Public Works2045-190Hodgen Rd Improvements – Black Forest to MeridianDesign and construct surface treatments and features that address the higher accident rate including multiuse shoulders and improving sight distance with horizontal and vertical improvements, include drainage features, and add turn lanes and intersection improvements where needed. At Roller Coaster and Hodgen Rd, design and construct a signal/roundabout and intersection improvements. Evaluate and construct improvements needed to meet current ADA standards.$29,000,000
El Paso County Public Works2045-211ITS programDesign and construct an ITS, which would allow for an integrated and centrally controlled traffic management system, sensors for traffic counts, incident management, etc. This may require installing fiber optic cable, radar, cameras, signal control upgrades and accessory equipment and equipment at DWP to monitor and control the system to better manage traffic efficiency and capacity. $5,000,000
El Paso County Public Works2045-250Judge Orr/Blue Gill Dr Intersection Realignment ProjectRealign the US24 East/Blue Gill Dr intersection to Judge Orr Rd. Project includes design, clearances, and construction.$6,369,002
El Paso County Public Works2045-193Lake Woodmoor DrFrom Woodmoor Dr to CO105, design and construct improvements to sight distances and intersections, resurface pavement, maintain drainage, and add multimodal facilities. Evaluate and construct improvements needed to meet current ADA standards.$10,000,000
El Paso County Public Works2050-074Major Road and Bridge Reconstruction – Phase 1This capital program includes road and bridge projects that improve road surfaces, update to current engineering standards and are beyond normal road maintenance. These projects may also install shoulders, regravel and grade gravel roads, convert gravel to paved roads, provide safety edges, enhanced striping, measures to prevent roadway departers, or reconstruct a roadway surface.  $18,800,000
El Paso County Public Works2050-075Meridian Rd – Latigo Blvd to Hodgen RdDesign and construct a project to bring the roadway to current 2-lane arterial standards, including sight distance, horizontal and vertical improvements, surface paving (existing gravel areas), add shoulders, drainage and intersection improvements, add auxiliary lanes and multimodal improvements.$28,200,000
El Paso County Public Works2050-076Meridian Rd S Gravel Road Conversion – Bradley Rd to Drennan RdThis gravel road segment has too many trips to safely function.  The gravel road needs to be paved and brought up to current standards.  The project will design and construct a gravel road conversion to paved roads with multiuse shoulders, safety improvements, turn lanes and auxiliary lanes, intersection and drainage and water quality improvements. $5,000,000
El Paso County Public Works2045-201Mesa Ridge Pkwy Improvements: Powers Blvd to Marksheffel RdComplete the connection between Powers Blvd (CO21) and Marksheffel Rd by designing and constructing a 2-lane urban principle arterial including intersection and auxiliary lane improvements, multimodal improvements, drainage and water quality improvements, and installation of bridge/s if needed.$15,000,000
El Paso County Public Works2050-077North Calhan Hwy from US24 to Paint Mine RdConstruct paved shoulders, improve driving surface, drainage, intersection improvements and provide multimodal features.$7,100,000
El Paso County Public Works2050-078Old Stage Rd from MP 0.75 to MP 4.157Re-gravel, grade, and drainage improvements.$7,300,000
El Paso County Public Works2023-018Pedestrian Crossings ImprovementsUpgrade 24 pedestrian crossings with MUTCD compliant signals and audible countdown pedestrian signals, ADA improvements and other safety features at high priority pedestrian crossing locations.$10,982,284
El Paso County Public Works2050-079Peyton Area Roads – Railroad, Front & Main StreetsReconstruct roadway for appropriate lane configuration, intersection and drainage improvements and consistent cross section including multimodal accommodations.$4,000,000
El Paso County Public Works2050-080Preconstruction Funding – Phase 1This capital program Includes activities to get projects shovel ready, often for grant funding or developer constructed improvements.  These projects may include design, corridor studies, safety analysis, ROW and/or required federal clearances. $18,800,000
El Paso County Public Works2022-021Road Rumble Strips and Epoxy StripingThis is a maintenance project with various locations for rural road centerline rumble strips and epoxy striping.$500,000
El Paso County Public Works2050-081Safety and Multimodal Program – Phase 1This capital program includes analysis, study, engineering and construction of intersection, multimodal, and corridor “spot” improvements to mitigate safety and traffic flow deficiencies. Proposed projects of this type will include the construction of traffic signals, roundabouts, auxiliary traffic lanes, traffic calming features, trails, multiuse shoulders, sidewalks and other geometric improvements. These projects may also install guard rail, construct/reconstruct medians, and install traffic control devices where warranted to improve bike and pedestrian crossings, emergency repairs, traffic operations and safety.$18,800,000
El Paso County Public Works2050-082Safety program – epoxy marking, multiuse shoulders, safety edges on rural roads, etc.Program project to improve safety for all users with FHWA safety countermeasures and other safety, operational and ADA improvements.$500,000
El Paso County Public Works2045-208Security Blvd at Willis DrTraffic signal replacement and intersection reconstruction/safety improvement. Replace signal equipment, auxiliary lane improvements, drainage improvements and pedestrian improvements.$1,500,000
El Paso County Public Works2050-083Stapleton Dr/Briargate Pkwy Improvements – Black Forest Rd to Vollmer RdConstruct new roadway connection, drainage, upgrade traffic signal, and multimodal features.$38,000,000
El Paso County Public Works2045-215Vollmer Rd Improvements: Marksheffel Rd to Shoup RdBring roadway to current 2-lane arterial standards, sight distance, horizontal and vertical improvements, surface paving (existing gravel areas), shoulders, drainage and intersection improvements, auxiliary lane improvements, multimodal improvements.$48,000,000
El Paso County Public Works Parks & Community Services Department2024-166Arroya Ln/Woodmen Hills/Rock Island Regional TrailsStarting Vollmer Rd and Arroya Ln at its intersection with the Sand Creek Regional Trail, this 5.3-mile Secondary Regional Trail follows Arroya Ln east past the Retreat at Timber Ridge and Sterling Ranch developments before turning south through Sterling Ranch, then eastward through the proposed The Ranch development, before turning southward through Bent Grass, past Woodmen Rd, before turning northeast along East US24 to Old Meridian Rd. This project will connect the City of Colorado Springs and Falcon with a contiguous non-motorized trail. It will connect to 5 sidewalks, 3 trails, commercial developments, and several neighborhoods. $2,820,000
El Paso County Public Works Parks & Community Services Department2050-084Black Forest Regional TrailAt 6.25 miles in length, this primary regional trail begins at CO83 and continues along Shoup Rd where it terminates at its connection to the Pineries Open Space and Black Forest Section 16 at the intersection of Shoup Rd and Vollmer Rd. Project includes design, clearances and construction. $8,500,000
El Paso County Public Works Parks & Community Services Department2050-085Crews Gulch Regional TrailThis 2.85-mile section of the primary regional trail begins where the existing Crews Gulch Regional Trail ends, at the intersection of Fountain Mesa Rd and Fontaine Blvd. The trail continues east along Fontaine Blvd to Marksheffel Rd at Lorson Ranch, where it connects with the proposed Jimmy Camp Creek Regional Trail. Project includes design, clearances and construction. $4,500,000
El Paso County Public Works Parks & Community Services Department2050-086Eastonville/Latigo Regional TrailsA mixed land use trail in nature, the Eastonville Regional Trail starts in an urbanized environment at Woodmen Rd and runs north along Eastonville Rd, connecting to Falcon High School and Falcon Regional Park. Entering a more rural area, the trail then continues to northward the existing Latigo Trails Open Space, where the trail turns westward and connects to Pineries Open Space, utilizing road rights-of-way and proposed property easements. Project includes design, clearances and construction. $8,250,000
El Paso County Public Works Parks & Community Services Department2045-182Fountain Creek Regional TrailAn 8-foot-wide multi-use trail, the Fountain Creek Primary Regional Trail begins at the El Pomar Youth Sports Complex in Colorado Springs and travels southward 24.90 miles through the City of Fountain to the El Paso/Pueblo County line. Approximately 14.55 miles of the trail is complete and finished with crusher fines surfacing. This project will complete the southernmost 10.40 miles of trail and will constitute the last segment of the Colorado Front Range Trail through El Paso County Public Works. Primarily surfaced in crusher fines, the trail will connect to 2 transit stops, one Park and Ride location, and 3 parks/open spaces.  Project would be conducted in partnership with the City of Fountain and possibly the Fountain Creek Watershed District.$5,200,000
El Paso County Public Works Parks & Community Services Department2045-216Fox Run Regional Trail (Cherry Creek)The 12.65-mile-long Fox Run Regional Trail begins at the intersection of Old Denver Rd and Baptist Rd, continuing east 1.7 miles as the completed 8-foot-wide sidewalk along Baptist Rd, before turning north through Promontory Pointe, where it shares a trail corridor with the proposed Jackson Creek Regional Trail. The trail then turns east through Sanctuary Point, connecting to Fox Run Regional Park, utilizing a 1-mile long completed section of crusher fine-surfaced trail. The trail leaves the park, continuing east along Hodgen Rd before crossing Hodgen Rd and turning south through the proposed Flying Horse North development where it connects to the existing Black Forest Regional Park trail system. $4,884,000
El Paso County Public Works Parks & Community Services Department2050-087CO94 Regional TrailApproximately 16.6 miles in length, the CO94 Regional Trail connects the City of Colorado Springs to the Town of Ellicott, including possible connections to Schriever Air Force Base and the Mayberry development.  The trail starts at the intersection of CO94 & East US24 and runs east along CO94 before ending at the Town of Ellicott. Project includes design, clearances and construction. $13,000,000
El Paso County Public Works Parks & Community Services Department2045-191Jackson Creek Regional TrailThis proposed contiguous non-motorized regional trail will connect the City of Colorado Springs and the Town of Monument.  Approximately 9.38 miles long, excluding alternate routes, this 8-foot-wide Tier I trail begins at its intersection with the New Santa Fe Regional Trail, travels east on CO105 before turning south along Jackson Creek Pkwy. At Higby Rd, the trail turns east before turning south into the Home Place Ranch development along Gleneagle Dr. The trail then continues south through an existing trail easement, crosses Baptist Rd before turning southwest near Jessie Dr following open spaces to Struthers Rd. The trail then splits into two sections, one heading west under I25 to the New Santa Fe Trail, the other heading south along Struthers Road to North Gate Blvd and the City of Colorado Springs trail system. $4,418,000
El Paso County Public Works Parks & Community Services Department2050-088Palmer Divide Regional TrailBeginning at the Pineries Open Space Trailhead, this 10.5-mile primary regional trail connects the Pineries Open Space to Homestead Ranch Regional Park. Its Pineries location allows it to make further connections southward to Black Forest Section 16 and the Sand Creek Regional Trail. Utilizing the existing singletrack trail loop in Pineries Open Space, the trail continues northeast through Black Forest Reserve, crossing Meridian Rd at a proposed underpass, where it continues northeast where it connects to the existing Woodlake portion of the trail.  From the Woodlake Trailhead, the trail turns east along Hodgen Rd and continues to through subdivisions to eventually connect to the Homestead Ranch Regional Park. Project includes design, clearances and construction. $7,500,000
El Paso County Public Works Parks & Community Services Department2050-089Sand Creek Regional TrailApproximately 5.55 miles long, this 8-foot wide primary regional trail commences along Sand Creek north of Woodmen Rd at the City of Colorado Springs/El Paso County Public Works line, follows Sand Creek north to Arroyo Ln, where it continues along Vollmer Rd to Burgess Rd and connects to the Black Forest Section 16. Ultimately, the trail will allow contiguous non-motorized connections to Pineries Open Space and the Palmer Divide Regional Trail, which is proposed to connect to Homestead Ranch Regional Park. It will connect to the City trail system at Woodmen Rd, 2 bike lanes, 1 school, 2 parks/open spaces, 3 trails, commercial developments, and several neighborhoods along Sand Creek. Project includes design, clearances and construction. $6,500,000
El Paso County Public Works Parks & Community Services Department2050-090South Powers TrailCommencing at Clear Spring Ranch, this 9.8-mile primary regional trail travels northward along the planned South Powers Blvd right-of-way corridor, ending at Powers Blvd and Fontaine Blvd where it connects to a proposed extension of the Crews Gulch Regional Trail. This trail would thus allowing for future connections to other primary and secondary regional trails in the area. Project includes design, clearances and construction. $14,250,000
El Paso County Public Works Parks & Community Services Department2050-091Ute Pass Regional TrailA important urbanized portion of the Ring the Peak Trail System, this particular project would focus on the last remaining unfinshed 2-mile section of the Ute Pass Regional Trail. Commencing at the intersection of West US24 and Fountain Ave in Cascade, the trail continues southeastward along the West US24 corridor, where it then turns southward along French Creek where it makes a connection to Longs Ranch Road and then the existing terminus of the Ute Pass/Ute Indian Trail. Project includes design, clearances and construction. $10,000,000
El Paso County Public Works/Private2045-231Black Forest Rd Widening: Old Ranch Road to ShoupExpand two-lane minor arterial to a 4-lane major arterial.$55,000,000
El Paso County Public Works/Private2050-092Drennan Rd Gravel Road ConversionDesign and construct improvements to Drennan Rd including converting the gravel road to pavement and bringing the road to current standards, adding multiuse shoulders, safety improvements, turn lanes and auxiliary lanes where needed, intersection, drainage and water quality improvements. This important east/west connection is one of few roads in the southern part of county that connect residents, agricultural products and military employees/contractors access to four bases. $43,000,000
El Paso County Public Works/Private2050-093Elbert Rd – US24 to County Line Rd N ImprovementsElbert Rd makes an important connection from US24 East going to Douglas County and connects to CO86. Design and construct a project to bring the roadway to current 2-lane arterial standards, improve sight distance, horizontal and vertical improvements, add multiuse shoulders, drainage, water quality, intersection improvements, and auxiliary and turn lanes.$70,000,000
El Paso County Public Works/Private2045-236Grinnell Blvd: Goldfield to Powers Blvd (CO21)Design and construct two additional lanes with multimodal features and improve the intersection at Powers Blvd (CO21).$10,900,000
El Paso County Public Works/Private2050-094Meridian Rd – Bradley Rd to Squirrel Creek RdNew road connection needed.  Design and construct the new 2-lane road segment to include intersection and auxiliary lane improvements, pedestrian improvements, drainage and water quality improvements.$42,000,000
El Paso County Public Works/Private2045-210/2025-001Shoup Rd. Improvements CO83 to Meridian RdResurface and maintain the road segments. Design and construct features that address the higher accident rate including shoulders and improving sight distance with horizontal and vertical improvements, include drainage features, and add turn lanes and intersection improvements where needed. Design and construct new segment to Meridian Rd. Add multimodal improvements. Evaluate and construct improvements needed to meet current ADA standards.$97,517,887
El Paso County Public Works/Private2045-213Stapleton Dr/Briargate Pkwy: Towner Ave to Meridian RdWhere needed, design and construct new road segments and where needed design and construct additional through lanes to increase capacity from 2 to 4 lane expressway standard to reduce existing congestion, drainage and intersection improvements, auxiliary lane improvements, multimodal improvements.$48,000,000
El Paso County Public Works/Private2050-095Walker Rd from Steppler Rd to Black Forest RdConstruct paved multiuse shoulders, improve driving surface, drainage, turn lanes, accel and decel lanes, and intersection improvements.$40,000,000
Envida2025-002Coordinated Mobility On-Demand in the Pikes Peak RegionOperating funds for fiscal years 2025, 2026, and 2027 to deliver additional rides for older adults and individuals with disabilities and to meet the financial match requirements of AAA and 5310 transportation programs.$624,492
Fountain2023-009Fountain ADA ImprovementsSidewalk and Pedestrian Ramp Construction and Reconstruction to enhance connectivity and meet ADA requirements within the following 2045 LRTP Corridors: Fortman Ave — Fountain Mesa Rd to Medicine Bow Ave. Fountain Mesa Rd — Mesa Ridge Pkwy to Fortman Ave. Medicine Bow Ave — Fountain Mesa Rd to Woodstock St. Old Pueblo Rd — Link Rd to Illinois Ave. Southmoor Dr. — US85/87 to US85/87.$159,700
Fountain2021-005Link Rd ReconstructionLink Rd from Old Pueblo Rd to Kane Rd Reconstruction – Roadway reconstruction, roadway widening (2 lanes to 3 lanes), safety improvements, drainage improvements, signalization improvements, bike lanes and sidewalk. Three phases.$5,618,726
Fountain2045-221Old Pueblo Rd Reconstruction from Link Rd to Illinois Ave6,900 foot long; 2 travel lanes; 2 bike lanes; 25 to 30 mph; minor arterial; 6 inch vertical curb; 6 foot attached/detached sidewalk. Full reconstruction to address significant slippage cracking, longitudinal cracking, alligator cracking, block cracking, potholes, distortions and rutting. This is a critical roadway that serves numerous residents in the following adjacent subdivisions Ventana, Tera, Fountain Farms and Fountain Industrial Park. Turn lanes will be necessary at the intersections to ensure the through lanes will not experience interrupted flow as they do today.$13,000,000
Fountain2045-222Southmoor Dr Reconstruction from US85/87 to US85/8712,100 foot long; 2 lanes; 25 to 30 mph; major collector; vertical/mountable curb; 6 foot attached/detached sidewalk. Full reconstruction to address significant transverse cracking, longitudinal cracking, alligator cracking and edge cracking. This is a critical roadway that serves numerous residents and several businesses including Fountain Valley Senior Center, Anderson Brothers Subdivision, Beckett Development, Fountain Plaza North, Fountain Commons, Pedro Subdivision and the Southmoor Subdivision.$19,000,000
Green Mountain Falls2050-096Belvidere Avenue Right-of-Way ImprovementsPlanning/design and construction.$275,000
Green Mountain Falls2050-097El Paso Ave Bridge ReplacementPlanning/design and construction.$875,000
Green Mountain Falls2050-098El Paso Trail and Iona Ave Roads ImprovementEl Paso Trail Road Drainage Improvements (paving, graveling, ditch, easements) (Iona Ave culvert replacement).$173,580
Green Mountain Falls2050-099Green Mountain Falls Transportation Safety Improvement ProjectThe Town of Green Mountain Falls seeks to create improvements to pedestrian, bicycle and vehicular traffic through the impelmentation of reallignment and improvement of trails, widening of Ute Pass Avenue to include ADA pedestrian walkways and public transit infrastructure (bus shelters, etc.). $950,000
Green Mountain Falls2050-100Ute Pass Ave (Downtown) ImprovementsFrom Olathe St to Hotel St, improvements include curb, sidewalk, gutter/drainage, and parking.$365,000
Green Mountain Falls2050-101Ute Pass Ave Pedestrian Bridge Safety ImprovementsThis project will widen the road and widen/replace the bridge on Green Mountain Falls Rd to allow for pedestrian traffic on both sides.$225,000
Manitou Springs2023-011Creekwalk Trail Phase 6Creekwalk Trail Phase 6 – Lovers Lane/Wichita Parking Lot to intersection of Park Ave and Manitou Ave and intersection of Manitou Ave and Serpentive Ave to City Boundary at Serpentine Ave. The Creek Walk trail, which has the first 5 phases funded, is looking to continue performing topographical survey, ROW delineation, and trail design to continue the City’s efforts to connect the Creek Walk Trail through the City. The goal is to provide a 10′ wide concrete pavement path that aligns with Fountain Creek and provides for non-motorized connectivity through town.$230,000
Manitou Springs2045-223Crystal Park Rd ImprovementsThe first phase of the proposed Crystal Park Rd improvement plan is to install sidewalk, curb, gutter, and lighting that is missing on the North and East side from Old Crystal Park Rd to Sutherland Pl, and install a sidewalk, curb, gutter, and lighting from Sutherland Pl to Crystal Hills Blvd. A section of the 1.5 miles of Crystal Park Rd, a 2-lane road with a speed limit of 25 mph throughout, with a primarily residential and commercial function. Labeled as phase two, and part of phase one, of the Manitou Springs Crystal Park Rd Traffic Study.$698,610
Manitou Springs2023-010East Manitou Ave Pedestrian and Drainage ImprovementsEast Manitou Ave pedestrian and drainage improvements from intersection with El Paso Blvd (west) to on/off ramps on the east side of US24 Bypass. This section of Manitou Ave has proper lane widths and newer pavement, the primary focus of this project is for utility undergrounding, sidewalk widening, back-in angle parking opportunities, and operational improvements at the US24 off/on ramps.$2,620,000
Manitou Springs2045-224East Manitou Ave Pedestrian and Drainage Improvements Ph 2Sidewalk, curb/gutter, crosswalk, storm drainage, street lighting, and landscaping improvements, and undergrounding of electricity, telephone and cable lines on Manitou Ave from intersection with El Paso Blvd to overpass of US24 Bypass. Project costs also include traffic circle at Manitou Ave/El Paso Blvd intersection, plans/specs and bid document creation and construction administration services. Project area approximately 5,005 LF total.$1,326,700
Manitou Springs2045-255El Paso Blvd Pedestrian and Drainage ImprovementsDesign and construct, transportation-related improvements to 7900 LF of El Paso Blvd from Manitou Ave to the City boundary. Roadway improvements including curb/gutter, sidewalk, crosswalks, storm drainage, street lighting, landscaping improvements, and undergrounding of electricity, telephone, and cable lines.$1,900,000
Manitou Springs2045-256Lovers Lane and Creek Walk Trail Pedestrian and Mobility ImprovementsDesign transportation-related improvements to 1500 LF of Lovers Lane from Canon Ave to El Paso Blvd. Project includes survey, ROW acquisition, design, and construction. Roadway improvements including multimodal trail (Creek Walk Trail), curb/gutter, crosswalks, storm drainage, street lighting, landscaping improvements, and undergrounding of electricity, telephone, and cable lines.$1,300,000
Manitou Springs2050-102Manitou Ave Safety and Mobility Improvements Phase 1Safety and mobility improvements.$1,500,000
Manitou Springs2021-007Ruxton Ave ReconstructionThe Ruxton Ave Pedestrian and Drainage Improvements is a project to upgrade Ruxton Ave from Manitou Ave to the Cog Railway. The project involves the reconstruction of Ruxton Ave with upgraded sidewalks, utilities, approach roadways and parking opportunities. It is the intent of the project to implement the findings of the mobility study presently underway. This may include transit and traffic management alternatives.$4,303,268
Manitou Springs2023-043Serpentine E Dr Roadway ImprovementsPreliminary design, conceptual plans, public engagement and survey of the Creek Walk/Serpentine area for improvements to connectivity to the City’s western boundary. Provide connection to the existing Creek Walk Trail project, roundabout, Rainbow Falls and Higgenbotham Park. The existing Creek Walk Trail begins at the City’s eastern boundary, where it connects with the Colorado Springs Midland Trail, and then extends west to Manitou Springs’ Pool and Recreation Center at Schryver Park, adjacent to Garden of the Gods Pl/Manitou Ave. In November 2018, the Manitou Springs City Planning Commission adopted the Manitou Springs Creek Walk Master Plan (CWMP), which identified a preferred alignment to construct the remaining Creek Walk Trail segments from Schryver Park/Recreation Center to the City’s western boundary at Serpentine Dr, near the Rainbow Falls Cultural Site in El Paso County.$2,034,250
Monument2019-028Jackson Creek Pkwy ExpansionJackson Creek Pkwy is a major north south road from Baptist Rd to CO105. The project is intended to increase the 2 lane segment to 4 lanes to ensure safety and capacity. The portion of Jackson Creek Pkwy south of Higby Rd is in the jurisdiction of Triview Metropolitan District. North of Higby Rd is the jurisdiction of the Town of Monument. The scope of work for this portion of the project consists of preconstruction and mitigation phases only. Additionally, the preconstruction and construction phases of a bicycle/pedestrian facility will be completed.$7,141,064
Multiple Agencies2050-103Powers Blvd Extension – CO83 to Voyager PkwyConstruct Powers Blvd from CO83 (Interquest Pkwy) to Voyager Pkwy to connect with I25.$140,000,000
Multiple Agencies/Private2045-258Powers Blvd (CO21) – South Extension to Rail Park (west of I25)Design, ROW acquisition and construction of a 2-lane arterial interim section of S Powers (CO21) per the PEL, including multimodal, water quality, and other features to reduce traffic on other area roads and provide a redundant link to I25. This road will serve freight from Powers north, Colorado Springs Airport and the freight distribution centers around the airport. $38,600,000
Multiple Agencies2045-248Rail Station Design/Construction ProjectThe project limits are to be determined in conjunction with the Southwest Chief Through Car Study and service development planning for FRPR. Project includes planning, design, and construction of a rail station in the Pikes Peak Metropolitan Planning Area. Final approval to spend funding would be via addition to the TIP.$5,000,000
Multiple Agencies2045-246US24/Peterson Rd InterchangeConduct environmental clearance, design services and construction from the US24 ramps intersecting with Peterson Road to the Peterson SFB North Gate. The project will accommodate pedestrian and bicycle infrastructure and include improvements for transit service up to the gate entrance.$16,500,000
Palmer Lake2021-006Palmer Lake Elementary School Roadway & Safety ImprovementsImprovements to two roads, Upper Glenway and Pie Corner which are connected to CO105 and provide the main route to Palmer Lake elementary school. The length of the road is 1,350 feet of which 220 feet is the student pickup and drop off area. Residential location where the speed limit is 25 mph, except approximately 600 feet of which is in a school zone and is 2 0mph during school hours. Both roads involved are 2-lane roads except in the school drop off location where the road widens slightly. Includes new asphalt, upgrades to existing sidewalks and improving storm water runoff. Will specifically include improved signage about school zone speed and crosswalk signs to where the children are being dropped off. Possibly solar powered flashing lights for school zone speed and crosswalk. Current sidewalks will be replaced for new ADA compliance sidewalks which will have a ramp at the entrance to the school.$10,000
Palmer Lake2023-007Spruce Mountain Rd ImprovementsSpruce Mountain Rd from W Perry Park Rd to Douglas County Line. Intersects with County Line Rd – Spruce Mountain Rd is a principal arterial that connects Palmer Lake with Larkspur; it is also heavily used when I25 backs up. Currently it is configured as a 2-lane road and has no shoulder on either side of the road. Improvements will include a new driving surface as well as a bike lane. Safety improvements will be turn lanes onto County Line Rd, which will improve traffic flow when there is a train. The rest of the 2,100 feet will still be 2 lanes but shoulders be widen and a bike added on one side. The roadway itself is very old and still has concrete under the pavement that used to be the Old Denver Hwy. which is creating heaves in the roadway. These improvements will help ease the congestion when the Interstate is backed up. $1,499,996
Palmer Lake2050-104Palmer Lake County Line Rd Widening and Safety ProjectThe County Line Rd widening and safety design and construction project is approximately 2/3 of a mile, from Spruce Mountain Rd to the top of the hill just past the Greenland Open Space where El Paso County Public Works begins maintenance, a minor arterial roadway.$2,391,000
Palmer Lake2050-105Palmer Lake Forest View Roadway Improvement ProjectThe Forest View roadway improvement design and construction project is approximately .5 mile, from Red Rocks Ranch Rd to Douglas Ave, a major collector roadway.  $1,460,000
Pike Ride2025-004Enhancing Micromobility Accessibility; Strengthening Transportation Demand ManagementThe Enhancing Micromobility Accessibility; Strengthening Transportation Demand Management project, with a focus on PikeRide’s existing public ebike share is an initiative aimed at improving transportation options within Colorado Springs and Manitou Springs. This project combines principles of micromobility, accessibility, and TDM to create a more efficient, sustainable, and inclusive urban transportation system.$267,375
PPACG2019-096Mobility Management – 5310Mobility management for specialized transit services using FTA Seciton 5310 funding.$1,966,745
Private2045-05421st St Roadway Improvements: US24 South to Lower Gold Camp RdWiden 21st St to a 4-lane roadway from US24 south to Lower Gold Camp Rd. Construct new sidewalk, curb, gutter and bike lanes as none exist. Project will also address drainage deficiencies as water currently sheet-flows off the roadway into curbside ditch or unimproved property.$6,600,000
Private2050-106Bandley Rd Reconstruction – Santa Fe Dr to Mesa Ridge Pkwy20,500 foot long; full reconstruction and widening of Bandley Rd from Santa Fe Dr to Mesa Ridge Pkwy to address rutting, significant longitudinal cracking, edge cracking, transverse cracking, and alligator cracking and to upgrade the frontage road to a minor arterial from a collector, consistent with the Fountain Transportation Master Plan. Widening will add a center turn lane and upgrade to the minor arterial section to include 2 lanes in each direction with a 5 foot shared use shoulders. The project will enhance an I25 redundant route, improving incident management, safety, and emergency response times, and will provide direct transit hub (south end of the corridor) connectivity.$30,000,000
Private2050-107C&S Rd Reconstruction – US85/87 to Mesa Ridge Pkwy17,000 foot long; full reconstruction and widening of C&S Rd between US85/87 and Mesa Ridge Pkwy to address rutting, significant longitudinal cracking, edge cracking, transverse cracking, and alligator cracking and to upgrade to collector to a minor arterial, consistent with the Fountain Transportation Master Plan. Widening will take a 2-lane section to a 5-lane section with 2 lanes in each direction, a center turn lane, and a 5 foot shared use shoulders. The project will complete an important existing east-west connector route to support incident management, to reduce congestion, and improve safety, resiliency, travel time reliability and emergency response times.$35,001,000
Private2050-108Fountain Mesa Rd Reconstruction – Lake Ave to C&S Rd5,280 foot long; full reconstruction to address rutting, significant longitudinal cracking, edge cracking, transverse cracking and alligator cracking. Maintenance efforts and disruptions to the traveling public will be minimized if reconstruction is performed. This is a critical roadway that serves military personnel in the area as well as residents in the following adjacent subdivisions Markets at Mesa Ridge Pkwy (business district) and Country Club Heights East subdivision. This will complete maintenance improvements to the minor arterial section, including 5 foot shared use shoulders,  between Mesa Ridge Pkwy and Ohio Ave and improve safety along the segment.$12,000,000
Private2045-102Hancock Expwy Realignment: Clarendon Dr to Chelton RdConstruct street and drainage improvements by extending Chelton Rd south to Drennan Rd and realigning Hancock Exwy east from Monica Dr/Claredon Dr to new Chelton Rd.$6,600,000
Private2050-109Squirrel Creek Rd Extension – Fountain Mesa Rd to Jimmy Camp Rd6,000 foot long; extend Squirrel Creek Rd from Fountain Mesa Rd to Jimmy Camp Rd as an arterial roadway with a 5-lane section including 2-lanes in each direction, a center turn lane, and a 5 foot wide shared use shoulder to include construction of a new bridge over Jimmy Camp Creek Rd. The project will complete an important east-west connection consistent with the Fountain Transportation Master Plan, and will provide a complete redundant route, reduce congestion, and improve incident management, travel time reliability, and emergency response times.  $21,000,000
Regional2050-116Alternate Modes – Pooled FundsAlternate modes projects and/or products within the MPO region.$7,000,000
Regional2050-114Marksheffel Rd Improvements – Woodmen Rd to N Carefree CirWiden Marksheffel Rd from Woodmen Rd to N Carefree Cir Include enhanced bike and pedestrian accommodations for the length of the corridor and provide safe crossing opportunities at intersections.$47,000,000
Regional2050-110Midland Trail ImprovementsMulti-jurisdictional trail program to extend, realign, widen, reconstruct, and construct trails, access to trails, connections to attractions or other portions of the trail network, crossings, wayfinding, ADA improvements and other functional enhancements. May entail engineering, land procurement, construction and ancillary trail activities.$1,000,000
Regional2050-115Planning – Pooled FundsPlanning projects and/or products within the MPO region.$2,000,000
Regional2050-117Safety and Congestion Management – Pooled FundsSafety and congestion management projects and/or products within the MPO region.$20,000,000
Regional2050-111State and Federal Discretionary Grant Match Fund – Phase 1This program could be available for all member governments and could be used for local matching funds for projects. The State or Federal Discretionary Grant Match Fund Program could be used to fulfill local match requirements for discretionary grants awarded by the State of Colorado (programs pending development) or the Federal government (e.g., INFRA, RAISE, CRISI grants) or future grant opportunities resulting from a federally declared disaster. The program is not intended to provide local match for revenue allocations administered by PPACG.$1,000,000
Regional2050-112Woodmen Rd Improvements – Powers Blvd to US24Safety and multimodal improvements on Woodmen Rd from Powers Blvd to US24. Widening from Golden Sage Rd to US24.$52,948,426
Regional/Private2050-113Ray Nixon Powerplant Road/Extension west of the Future I25/CO21 (Powers)Ray Nixon Powerplant Road/Extension west of the future I25/CO21 (Powers).$25,000,000
Woodland Park2045-237American Discovery Trail ConnectionConstruct a 550 foot long, 8 feet wide asphalt trail from US24 (existing sidewalk) to the Fountain Creek Open Space and connect to the American Discovery trail.$85,900
Woodland Park2023-041Pedestrian Infrastructure – Sidewalks: Browning AveThe project scope includes the provision of all labor, tools, equipment, materials, and supervision required to install sections of sidewalk that do not currently exist along Browning Ave.$330,756
Woodland Park2045-238CO67 Corridor Improvements – Phase IIThe CO67 Phase II project is to widen the highway from 2-lanes to 4-lanes including dedicated left turn lanes, bi-directional center turn lane; accel/decel lanes; and an underground stormwater system. This multi-modal project includes sidewalks on the west side connecting pedestrian facilities with Evergreen Heights Drive and Stone Ridge Village.$3,000,000

Projects by Type

For mapping and categorization purposes, projects were classified by their primary project type and a secondary project type based on the major elements of the project. Note that because many projects were assigned two project types, when added the following percentages will be more than 100%. In addition, although the projects were only designated to a maximum of two project types, many projects have multiple elements and could have been classified as several project types. For example, a project to improve roadway operations may also be a critical safety project but also may contain sidewalk or other bicycle/pedestrian features. See the project descriptions in Table 8-1 for details on particular projects.

Figure 8-1 depicts the number of projects by project type per the following text.

Figure 8-1: Projects by Type

A bar chart showing the number of projects by type in the 2050 long range transportation plan.
Click here for an accessible version of Figure 8-1: Projects by Type

The first and second goals of the LRTP discuss the preservation and enhancement of the regional transportation system and providing efficient and fully connected to transportation. To fulfill those goals, nearly 44% of the fiscally constrained list is roadway projects (103 projects). Nearly 22% (50 projects) of projects are classified as roadway operational improvements, 12% (28) are capacity and 11% (25) are preventative maintenance or reconstruction projects. Many of these projects also increase resiliency and redundancy.

Of the capacity projects, defined as projects that create new roads or road lanes, eight are anticipated to be fully or partially paid for with private funding. Five are CDOT projects, two of which are funded or partially funded in the current TIP and one of which is the construction phase of that TIP project. Of the remaining projects identified to be sponsored by local jurisdictions or multiple agencies, two are partially or fully funded in the TIP and one is a Phase 2 of an existing TIP project. Nine have already been approved by local voters to receive PPRTA funding and one is the construction phase of a current PPRTA project. PPACG anticipates the remainder to be identified for future PPRTA funding as they provide critical for critical connectivity, support safety by correcting outdated lane configuration, etc.

In addition to those roadway projects, nearly 14% (32) are interchange or intersection improvements projects; 10% (23) are bridge projects.

However, the LRTP goals also speak to providing multimodal transportation and maintaining a robust, equitable, and healthy system. The project selection process recognized that non-motorized, transit, and other transportation modes and the growth of those modes are critical to the overall system. In addition, there are several funding sources, including state MMOF and federal TAP funding that is designated specifically for alternate mode projects. Approximately 16% of projects (49) are classified as bicycle and pedestrian projects with an additional 13% (30) classified as multimodal improvement projects. Just over 8% of projects (19) are transit projects, although this does not include additional transit projects funded through FTA and transit-specific funding and identified in the Regional Transit Plan. Specific specialized transportation projects are also not included in this fiscally constrained list.

Understanding that safety is a critical issue for the Pikes Peak Region, 27% of projects were classified as safety improvement projects and nearly 6% were classified as ADA Enhancements.

Finally, about 10% of projects (23) included transportation studies and plans or water quality, technology, or other transportation-related enhancements and one project could not be classified as it is a PPRTA funding pool that provides local match money for projects that receive state or federal discretionary grants.

Figures 8-2 through 8-6 illustrate the roadway, intersection improvement, bridge, active transportation, and safety projects in the region.

Figure 8-2: Roadway Projects

A map of the Pikes Peak region showing roadway projects in the 2050 long range transportation plan.
Click here for an accessible version of Figure 8-2: Roadway Projects

Figure 8-3: Intersection Improvement Projects

A map of the Pikes Peak region showing intersection improvement projects in the 2050 long range transportation plan.
Click here for an accessible version of Figure 8-3: Intersection Improvement Projects

Figure 8-4: Bridge Projects

A map of the Pikes Peak region showing bridge projects in the 2050 long range transportation plan.
Click here for an accessible version of Figure 8-4: Bridge Projects

Figure 8-5: Active Transportation Projects

A map of the Pikes Peak region showing active transportation projects in the 2050 long range transportation plan.
Click here for an accessible version of Figure 8-5: Active Transportation Projects

Figure 8-6: Safety Projects

A map of the Pikes Peak region showing safety projects in the 2050 long range transportation plan.
Click here for an accessible version of Figure 8-6: Safety Projects

Because most projects have multiple characteristics, it is difficult to identify how much funding is designated to specific projects types funding amount designated to different project types. It should be noted that several funding types may be used for a single project. For example, a project may use TAP funding to add sidewalks but STBG funding for roadway operational improvements.

Transit Project List

As previously noted, the Regional Transit Plan outlines 58 projects divided into short-term (20), medium-term (21) , and long-term (17) projects. The projects are categorized by the following investment themes:

  • Enhanced Transit Corridors
  • New Fixed Routes
  • Innovative Mobility Zones
  • Extend Service Span
  • Improve Capital Infrastructure
  • Improve Existing Route Frequency
  • New Crosstown Routes

These projects total $1.25 billion in capital costs between 2025 and 2050. The full project list and more detail can be found in Appendix B. Figure 8-7 depicts these projects.

Figure 8-7: Transit Projects

A map of the Pikes Peak region showing transit projects in the 2050 long range transportation plan.
Click here for an accessible version of Figure 8-7: Transit Projects

In addition, MMT, local jurisdictions, and CDOT have developed a project list for inclusion in the TCS. This list contains projects in the Pikes Peak Region that can help support CDOT transit goals and represents more aggressive implementation of the vision in the Regional Transit Plan positioned to take advantage of increasing funding streams. This list includes several service enhancement projects, including express bus service and localized circulators to create last mile connections. In addition, this list includes express and flex service as part of the Plains to Peak Corridor as well as several stop and station improvements such as mobility hubs and upgrades to existing connection points. The list is included as an addendum to the Regional Transit Plan, Appendix B.

Unfunded Project List

As noted, the projected funding for the region is not anticipated to sufficiently meet transportation needs. Projects included in Table 8-2, are those that have an identified need but no identified funding source. While these projects would be beneficial to the regional transportation system, funding is not available to implement them within this plan. The unfunded project list is not all-encompassing. There are known needs beyond the scope of the fiscally constrained and unfunded project lists; however, they may not be developed enough to include in the LRTP at the time of publication. As the LRTP is updated in future years, the fiscally constrained and unfunded projects lists will change as needed.

Funding estimates were included in Table 8-2 when available.

Project SponsorProject NameProject DescriptionEst. cost
CDOTPPACG Freight Study RecommendationsScope to be determined.TBD
Colorado Springs21st St Bridge over Bear CreekReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado Springs2nd St Bridge over Spring RunReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado Springs31st St Bridge Reconstruction over Spring RunReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado Springs31st St/Camp Creek Roadway and Trail Improvements – Kiowa St to Fontanero St Phase 2Reconstruct roadway and bridges along the corridor to accommodate conversion of the concrete channel to a naturalistic rock lined channel. Includes new off-street trail and wayfinding signage for the corridor.$10,000,000
Colorado Springs8th St/Cheyenne Blvd Intersection ImprovementsConstruct a roundabout at 8th St/Cheyenne Blvd intersection including appropriate pedestrian and bicycle crossings.TBD
Colorado Springs8th Street Improvements – US24 to Fountain Creek Phase 2Construct roadway, pedestrian, and bicycle improvements and a bridge replacement at Fountain Creek.$3,420,740
Colorado SpringsAcademy Blvd and Palmer Park Pedestrian ConnectionsImprove pedestrian facilities and crossings along Academy Blvd to improve access to Palmer Park.TBD
Colorado SpringsAcademy Bridge over Platte Phase 2Replace Academy bridge over Platte Ave in configuration that better accommodates pedestrian movements along Academy and access to transit, and conversion to quadrant road interchange.$64,320,000
Colorado SpringsAustin Bluffs Pkwy/Garden of the Gods Rd/Nevada Ave Intersection Improvements and Bridge Replacement Phase 2This project will improve traffic operations, multimodal access and safety for the intersection of Austin Bluffs Pkwy/Garden of the Gods Rd and Nevada Ave. The intersection will be designed based on the PPRTA3 Intersection Study. The project will also require a new bridge on Garden of the Gods Rd over Monument Creek due to condition issues and to accommodate new configuration. The project includes extension of the multi-use trail along Austin Bluffs Pkwy to the Pikes Peak Greenway and considers future enhanced transit connections along Nevada Ave.$25,000,000
Colorado SpringsBijou St Bridge over Shooks RunReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsCache La Poudre St Bridge Reconstruction over Monument CreekReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsCache La Poudre St Bridge Reconstruction over Shooks RunReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsCampus to Campus Corridor Phase 2Enhanced Transit Corridor including Mobility Hubs connecting PPSC  Transfer Centers (at South Academy Blvd and Interquest Pkwy) to USAFA Gateway Visitor Center. Routing generally following Academy Blvd, Voyager Pkwy, and Northgate Blvd as determined by further analysis.$32,000,000
Colorado SpringsCascade – Mark Dabling Connection (construction) Phase 2Extend Cascade Ave to the north to connect to Mark Dabling Blvd with two new bridges.$418,650
Colorado SpringsCheyenne Rd Bridge over Cheyenne CreekReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsColorado Ave Roadway Improvements Phase 2Reconstruct Colorado Ave to improve safety including arterial street traffic calming and enhanced pedestrian crossings Increase on-street parking, widen sidewalks, and enhance bike/ped wayfinding throughout the corridor.$3,400,000
Colorado SpringsColorado Springs Railroad Bridges Program Phase 2Repair/Rehabilitation/Replacement of railroad bridges due to condition issues (such as Uintah, Tejon, Nevada, Shooks Run) or for City required changes to accommodate other improvements.$50,000,000
Colorado SpringsCongestion and Incident Management – Phase 2This capital program includes analysis, study, engineering and construction to implement Citywide/Region-wide Transportation System Management to include ITS and other technical solutions to improve traffic operations, coordinate systems and improve safety. Improvements may include monitoring systems, hardware and software, message systems, metering, fiber optic cable, communication infrastructure, and specialized equipment and staff.TBD
Colorado SpringsCostilla and Cucharras St Improvements over Shooks Run Phase 2Improve Costilla St and Cucharras St, including replacing the bridge over Shooks Run and improvements at Nevada Ave, Weber St, Corona St, Prospect St, Institute St, and Cedar St intersections.$9,627,000
Colorado SpringsCottonwood Creek Trail Corridor Improvements – Union crossing Phase 2Design and construct a grade-separated crossing of Cottonwood Creek Trail at Union Blvd.$12,400,000
Colorado SpringsCresta Rd Bridge over Cheyenne CreekReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsCucharras St Improvements – Nevada Ave to Hancock AveImprove Cucharras St, including a new bridge over Shooks Run and intersection improvements.TBD
Colorado SpringsDawson Dr Bridge over Dry CreekReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsEmergency Bridge Fund – Phase 2The Emergency Bridge Fund addresses unfunded bridge needs and provide the City the ability to repair, replace, or rehabilitate a bridge that has a serious deterioration issue or safety concerns to the travelling public. Historically, Emergency Bridge Funds have been invested in replacement design and construction efforts. The funds have enabled the City to leverage other funding sources, advance design efforts on B-List projects, and address serious bridge needs.TBD
Colorado SpringsFillmore Pedestrian Safety Improvements Phase 2Implement recommendations of a safety study. Consider access management, access to transit, and safe crossings$10,000,000
Colorado SpringsFillmore St Roadway Improvements Phase 2The bridges over Monument Creek/Pikes Peak Greenway and bridges over the Union Pacific Railroad will be replaced due to condition. The project also includes a trail connection down to the Pikes Peak Greenway. The project will improve the existing sidewalks and pedestrian facilities and widen Fillmore St. from 4 to 6 lanes from Cascade to I25.$151,000
Colorado SpringsFontaine Blvd Improvements – Rolling View Dr to Sleepy Meadow DrUpgrade to arterial roadway standards.TBD
Colorado SpringsGarden Ln Bridge over Fountain Creek TributaryReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsGarden of Gods Rd Bridge over Monument CreekReplace bridge due to condition issue and widen to support intersection improvements at Nevada Ave.TBD
Colorado SpringsGold Camp Rd Bridge over Bear CreekReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsHancock Corridor Study and Implementation Phase 2Conduct a study to determine the desired function/role of Hancock Expwy between the airport and Downtown Colorado Springs considering vehicles use, enhanced transit corridor, bike and pedestrian connections, and desired land use.$10,000,000
Colorado SpringsHancock Expwy/Delta Dr/Circle Dr Intersection Safety ImprovementsConstruct intersection improvements to improve safety for vehicles and bicyclists.TBD
Colorado SpringsHolly Street New Bridge over Columbia DrainageReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsInterquest Pkwy Multimodal Improvements – I-25 to E Federal DrConduct an analysis to assess the traffic impacts to this area as a result of the northern extension of Powers Blvd to I25 and provide a concept to improve multimodal access to and between businesses and employers and improve safety and intersection operations.TBD
Colorado SpringsIntersection Improvements – Phase 2Construct improvements at intersections that will reduce delay, improve air quality, and enhance safety for both motorized and non-motorized traffic.TBD
Colorado SpringsLas Vegas St Bridge over Shooks RunReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsLas Vegas St Corridor Improvements – Ft Carson Spur to 1,200′ south of Janitell RdProvide roadway, intersection and bicycle and pedestrian improvements to Las Vegas St to address safety, drainage, and access.TBD
Colorado SpringsLas Vegas St Corridor Improvements – SH85/87 to Ft Carson SpurProvide roadway, intersection, and bicycle and pedestrian improvements to Las Vegas St to address safety, drainage, and access.TBD
Colorado SpringsMayhurst Ave Bridge over Cheyenne CreekReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsMesa Rd Improvements – Fillmore St to Uintah StImprove Mesa Rd with curb, gutter, sidewalk, bike lanes, and a shared use path.TBD
Colorado SpringsMurray Blvd and Bijou St Intersection ImprovementsDesign and implement a roundabout intersection at this location.TBD
Colorado SpringsNevada Roadway Safety Study – Uintah St to Fillmore StAnalyze alternatives and identify a concept for improving safety and mitigating traffic speeds on Nevada Ave between Uintah St and Fillmore St.TBD
Colorado SpringsOld Ranch Rd – Kettle Creek to Lexington Dr Shoulders and Sidewalk ImprovementsCompletes improvements to Old Ranch Rd between Kettle Creek and Lexington Dr by adding shoulders and sidewalks.TBD
Colorado SpringsOld Ranch Rd Improvements – Cordera Crest Ave to Union Blvd/Milam RdImprove Old Ranch Road operations and safety.TBD
Colorado SpringsOn-Street Bikeway Improvements – Phase 2The City’s Comprehensive Plan, ITP, Bike Master Plan and the Complete Streets ordinance strongly recommend streets be designed to accommodate safe and efficient bicycle travel/access. There are many locations in the city where safe and adequate bicycle travel and access are not provided or need enhancement. Proposed bikeway improvements will continue to include: improve and construct bike lanes in accordance with the ITP and the City’s Bicycle Plan; install on-street bicycle lanes and connections to off-street facilities to close gaps on the existing bike network; improve connections from on-street bike lanes to the Colorado Springs trail system and residential/commercial centers; and, develop/implement improved signage to provide better wayfinding for cyclists.TBD
Colorado SpringsPatty Jewett Trail – Cache La Poudre St to Patty Jewett Golf CourseConstruct a 12 foot shared use trail along Shooks Run between Cache La Poudre St and Patty Jewett Golf Course.TBD
Colorado SpringsPedestrian Bridge Reconstruction over Cache La Poudre StReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsPeterson Rd Multimodal Improvements – Dublin Blvd to Stetson Hills RdReconstruct sidewalk on one side of the road to provide a two-way shared-use path.TBD
Colorado SpringsPine Creek Trail Connection – Pikes Peak Greenway to Research Pkwy Phase 2Construct a shared use path along Pine Creek between Pikes Peak Greenway and Research Pkwy.$9,000,000
Colorado SpringsPlains to Peak Corridor Phase 2Enhanced Transit Corridor including Mobility Hubs connecting Manitou Springs to Falcon. Routing generally following Colorado Ave, Pikes Peak Ave, Platte Ave, and US24 as determined by further analysis.$19,200,000
Colorado SpringsPlatte Ave Reconstruction – Wahsatch Ave to Cascade AveReconstruct Platte Ave between Wahsatch Ave and Cascade Ave to one travel lane in each direction to increase pedestrian safety and improve intersection operations at Nevada Ave.TBD
Colorado SpringsPlatte Ave/Academy Blvd Interchange Conversion Phase 2Reconstruct Academy Blvd/Platte Ave interchange to be a quadrant road interchange to facilitate pedestrian movements along Platte Ave by removing ramps and across Academy by eliminating left turns on the bridge.$36,400,000
Colorado SpringsRangewood Dr Bridge over Cottonwood Creek TributaryReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsReplace and Upgrade Transit IT Equipment and Software Phase 2Maintain and upgrade existing transit hardware and software allowing for smart-cards, real-time bus information, traffic signal prioritization, etc. to improve efficiency and customer service.$23,310,000
Colorado SpringsRoadway Safety and Traffic Operations – Phase 2This capital program includes analysis, study, engineering and construction of intersection and corridor “spot” improvements to mitigate existing safety and traffic flow deficiencies. Proposed projects of this type will include the construction of traffic signals, roundabouts, auxiliary traffic lanes, traffic calming features, incorporation of multimodal enhancements, and other lower-cost geometric improvements. These projects may also install guard rail, construct/reconstruct medians, and install traffic control devices where warranted to improve traffic operations and safety.TBD
Colorado SpringsSaint Elmo Ave Bridge over Cheyenne CreekReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsSaint Vrain St Bridge over Shooks RunReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsSand Creek Trail Corridor Improvements – Palmer Park Blvd to Airport RdConstruct a new 12 foot trail to include pedestrian underpasses and pedestrian bridges.TBD
Colorado SpringsSidewalk Infill Improvements – Phase 2The City’s Comprehensive Plan, ITP) and the Complete Streets Policy strongly recommend streets be designed to accommodate safe and efficient pedestrian access. There are many locations in the city where safe and adequate pedestrian travel and access are not provided. Proposed pedestrian improvements will continue to construct missing pedestrian connections along transportation facilities, schools, and neighborhoods and will follow the Operations and Maintenance Division quadrant approach to improve safety and develop/implement improved pedestrian connectivity.TBD
Colorado SpringsSinton Trail Underpass at Centennial BlvdImprove Sinton Trail underpass under Centennial Blvd.TBD
Colorado SpringsStetson Hills Blvd – Marksheffel Rd to Luther RdExtend Stetson Hills Blvd from Marksheffel Dr east to Luther St as a complete street with bike and pedestrian facilities.TBD
Colorado SpringsStratton Ave Bridge over Cheyenne CreekReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsTech Center Dr/Rusina Rd/Pro Rodeo Dr Shared Use Path – Garden of the Gods Rd to Rockrimmon BlvdConstruct a shared use trail between Rockrimmon Blvd and Garden of the Gods Rd, generally along the alignment of Tech Center Dr.TBD
Colorado SpringsTempleton Gap Trail Connection – Templeton Gap Rd to Templeton Gap TrailConstruct a shared use path or upgrade and connect existing sidewalk along the west side of Union Blvd between Templeton Gap Rd and the Templeton Gap Trail.TBD
Colorado SpringsTerminal Southgate Enhanced Transit Corridor Study and Implementation Phase 2Evaluate options for implementing enhanced transit, options should include routing and operations, and alternate routing.$8,000,000
Colorado SpringsTransit Fleet Supplement Phase 2Fund replacement and expansion transit service vehicle purchases: diesel, gasoline, and any low or zero emission vehicles including supporting infrastructure technologies to fuel and charge.$125,680,000
Colorado SpringsTransit Service Enhancements – Phase 2Studies and service extension/expansion enhancements (including Comprehensive Operation Analysis, Alternate Transportation Implementation Study and other studies) and implementation to improve operations and/or to provide service extension/expansion enhancements to Military Installations, Major Employers, and Tourism Hubs and underserved areas as well as Nevada Ave, Academy Blvd, Platte Ave, or other corridors identified for consideration in ConnectCOS. This program aims to bring public transit in the Colorado Springs area to a higher level by providing direct, frequent, efficient, and reliable transit solutions that continue to focus on improving the existing service area, advancing high-frequency core transit corridors to create improved mobility options for the entire community, improving service hours and frequencies, and implementing new and advanced technologies to improve reliability and advance fleet upgrades.$50,000,000
Colorado SpringsTransit Stop and Station Improvements – Phase 2New or existing transit stops and stations; stop improvements could include, but not limited to, safety improvements, customer access, sidewalk connections, ADA-compliance, pre-board fare payment infrastructure, wayfinding, service kiosk, message boards, benches, trash receptacles, and shelters. Station examples include new/relocated stations or transfer centers at Chapel Hills Mall, Citadel Mall, Hancock/Academy, Pikes Peak SC and other Multimodal Hubs to support ConnectCOS Transit Vision Network including but not limited to Garden of the Gods Rd, PPSC, military bases, downtown and park and rides, and active transportation connections.$50,000,000
Colorado SpringsUintah St Multimodal Improvements – El Paso St to Institute StThe project includes the reconstruction of the Uintah St bridge over Shooks Run to include a trail underpass and ramps from the trail to street level.TBD
Colorado SpringsUnion Blvd Bridge over Cottonwood Creek TributaryReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsUnion Blvd/Circle Dr Bike Improvements – Monterey Rd to Fountain BlvdAddress gaps in bicycling infrastructure along south Union Blvd and Circle Dr, including a 2-way cycle track between Hancock Expy and Monterey Rd.TBD
Colorado SpringsUPRR Bridge over Nevada AveReplace bridge due to condition issue.TBD
Colorado SpringsUPRR Bridge over Shooks RunReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsUPRR Bridge over Tejon StReplace bridge due to condition issue.TBD
Colorado SpringsUPRR Bridge over Uintah StReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsVincent Dr Bridge over Cottonwood CreekReplacement or removal of bridge due to condition issue.TBD
Colorado SpringsWater St Bridge Replacement over Camp CreekReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsWestwood Blvd Bridge over Templeton Gap BasinReplacement or major rehabilitation of bridge due to condition issue.TBD
Colorado SpringsWoodmen Rd Multimodal Improvements – Orchard Valley Rd to Rockrimmon BlvdConstruct multimodal improvements including on-street bike lanes and sidewalks along Woodmen Rd between Orchard Valley Rd and Rockrimmon Blvd.TBD
El Paso CountyNon-motorized Projects Pool ProgramA program to implement non-motorized projects to improve safety and connectivity.$20,000,000
El Paso CountyBaptist Rd from Desiree Dr to Roller Coaster RdConstruct paved multiuse shoulders, improve driving surface, drainage, and intersection improvements.$28,500,000
El Paso CountyBradley Rd from Academy to GoldfieldReconstruct/construct roadway for appropriate lane configuration, intersection and drainage improvements and consistent cross section including multimodal accommodations.$70,000,000
El Paso CountyBridge Maintenance and Replacement Pool ProgramA program to design, preconstruction activities, and construct bridge maintenance and bridge replacements.$150,000,000
El Paso CountyBurgess Rd from Milam Rd to Meridian Rd (via Goodson/Rex)Construct paved shoulders, improve driving surface, drainage, intersection improvements and provide multimodal features.$71,000,000
El Paso CountyCurtis Rd from Judge Orr Rd to Falcon Hwy and Garrett Rd to Highway 94Construct paved multiuse shoulders, improve driving surface, drainage, and intersection improvements.$38,000,000
El Paso CountyData Collection Pool ProgramProgram to purchase equipment, contracts or software for data collections including but not limited to traffic counts, speed monitors, cameras, compliance with traffic rules, crash data or identification of crash hot spots,  etc. to allow data driving decision making. $12,000,000
El Paso CountyFountain Mesa Rd from Caballero Ave to Fontaine BlvdUrban drainage improvements, multimodal features & upgrade traffic signal.$9,000,000
El Paso CountyCO105 from Arrowwood Dr to CO83Construct paved multiuse shoulders, improve driving surface, drainage, and intersection improvements.$31,000,000
El Paso CountyInterchange at Academy Blvd and PPSC DesignPlan and design for a future grade separation.$4,500,000
El Paso CountyMajor Road and Bridge Reconstruction – Phase 2This capital program Includes road and bridge projects that improve road surfaces, update to current engineering standards and are beyond normal road maintenance. These projects may also install shoulders, regravel and grade gravel roads, convert gravel to paved roads, provide safety edges, enhanced striping, measures to prevent roadway departers, or reconstruct a roadway surface.  $18,800,000
El Paso CountyMeridian Rd from Hodgen Rd to Rex RdReconstruct/construct roadway for appropriate lane configuration, intersection and drainage improvements and consistent cross section including multimodal accommodations.$67,000,000
El Paso CountyMeridian Rd from Woodmen Rd to Woodmen Hills Dr ImprovementsReconstruct/construct roadway for appropriate lane configuration, intersection and drainage improvements and consistent cross section including multimodal accommodations.$19,000,000
El Paso CountyMilam Rd from Shoup Rd to Old Ranch RdConstruct paved multiuse shoulders, improve driving surface, drainage, and intersection improvements.$22,700,000
El Paso CountyOld Pueblo Rd from Link to I25 ImprovementsConstruct paved multiuse shoulders, improve driving surface, drainage, and intersection improvements.$57,000,000
El Paso CountyPavement Maintenance Pool ProgramA program to identify road segments needing pavement overlays, safety edges, striping, crack or chip sealing with the goal to extend the useful live a pavement.$120,000,000
El Paso CountyPreconstruction Funding – Phase 2This capital program Includes activities to get projects shovel ready, often for grant funding or developer constructed improvements. These projects may include design, corridor studies, safety analysis, Right of Way and/or required federal clearances. $18,800,000
El Paso CountyRampart Range Road from MP 18.8 to MP 21.1 and Loy CreekUpgrade the road from gravel to pavement, safety and drainage improvements.$4,700,000
El Paso CountySafety and Multimodal Program – Phase 2This capital program includes analysis, study, engineering and construction of intersection, multimodal, and corridor “spot” improvements to mitigate safety and traffic flow deficiencies. Proposed projects of this type will include the construction of traffic signals, roundabouts, auxiliary traffic lanes, traffic calming features, trails, multiuse shoulders, sidewalks and other lower-cost geometric improvements. These projects may also install guard rail, construct/reconstruct medians, and install traffic control devices where warranted to improve bike and pedestrian crossings, emergency repairs, traffic operations and safety.$18,800,000
El Paso CountySafety Implementation Pool ProgramA program to implement various safety improvements with a focus on high crash areas, intersections, and the use of FHWA Proven Safety Countermeasures.$50,000,000
El Paso CountyStormwater Master PlanDevelop a Stormwater Master Plan that includes hydrologic and hydraulic modeling, risk assessments, development of a CIP and cost estimates. $3,000,000
El Paso CountyStormwater Project Design and Construction Pool ProgramOngoing conditions assessments are determining improvements needed to address stormwater related to road runoff or regional pond needs. Design and construct project to address identified needs.$500,000,000
El Paso County PublicInterchange at Academy Blvd and PPSC ConstructionPreconstuction ROW and other permits and construction of the Interchange.$10,000,000
El Paso County Public WorksADA Compliance Program Phase 2Work will occur on a variety of roads in the unincorporated area within the MPO boundary to carry out an ADA Compliance Program.  Design and construct ADA improvements, missing sidewalk/trail connections, and intersection, signal and signing improvements. $150,000,000
El Paso County/Colorado SpringsBlack Forest Rd Improvements – Research Pkwy to Shoup RdScope to be determined.$55,000,000
Green Mountain FallsBridge ImprovementsSafety improvements study for 8 bridges. $50,000
Green Mountain FallsIntersection Improvements (Green Mountain Falls)Traffic engineering study. $75,000
Green Mountain FallsRoadway Safety and Traffic Operations (Green Mountain Falls)Traffic engineering study. $125,000
RegionalState and Federal Discretionary Grant Match Fund-Phase 2This program could be available for all member governments and could be used for local matching funds for projects. The State or Federal Discretionary Grant Match Fund Program could be used to fulfill local match requirements for discretionary grants awarded by the State of Colorado (programs pending development) or the Federal government (e.g., INFRA, RAISE, CRISI grants) or future grant opportunities resulting from a federally declared disaster. The program is not intended to provide local match for revenue allocations administered by PPACG.TBD
RegionalWoodmen Rd Improvements – Powers Blvd to US24 Phase 2Safety and multimodal improvements on Woodmen Rd from Powers Blvd to US24. Widening from Golden Sage Rd to US24.$47,051,574